Will protect the construction of site clearance for WHA Industrial Zone Nghe An

Pearl June 3, 2020 13:58

(Baonghean.vn) - Vice Chairman of Nghe An Provincial People's Committee Le Ngoc Hoa has just issued Notice No. 272 ​​dated May 27, assigning Nghi Loc District People's Committee to propagate and mobilize 3 households in Hamlet 4, Nghi Thuan Commune to hand over the site before June 10, 2020. After this deadline, if the households still do not hand over the site, Nghi Loc District People's Committee will have a plan to protect the construction and report to the Provincial People's Committee before June 15, 2020.

Accordingly, Vice Chairman of the Provincial People's Committee Le Ngoc Hoa praised the departments, branches and WHA Industrial Zone Nghe An Joint Stock Company for their efforts to implement the work according to the conclusions and directions of Vice Chairman of the Provincial People's Committee Le Ngoc Hoa at the working session with the people of Nghi Thuan commune. However, compared to the progress requirements, there are still some problems on the ground that need to be further reviewed and focused on to effectively resolve.

Overall perspective of WHA Industrial Zone Nghe An. Photo courtesy

Vice Chairman of the Provincial People's Committee Le Ngoc Hoa assigned the Nghi Loc District People's Committee to propagate and mobilize 3 households in Hamlet 4, Nghi Thuan Commune to hand over the site before June 10, 2020. After this deadline, if the households still do not hand over the site, the Nghi Loc District People's Committee will have a plan to protect the construction and report to the Provincial People's Committee before June 15, 2020. The district will complete the excavation and relocation of the remaining graves in June 2020; focus on mobilizing and relocating 194 graves in Tung Market Cemetery, to be completed in 2020.

The district reviews the records, specifically identifies the land type and land user for the land area donated for roads and intra-field canals in the past for all 16 households in Hamlet 4, Nghi Thuan Commune; completes and sends a document to the Department of Finance before June 5, 2020 to advise the Provincial People's Committee.

Assign the Department of Finance to advise the Provincial People's Committee on funding support for the area of ​​742 m2Land of 16 households donated for road construction and brick ditches before June 10, 2020.

The infrastructure of the industrial park has been synchronized, only a few households have not agreed to the land acquisition and clearance. Photo: PV

Regarding the construction of residential roads, the Vice Chairman of the Provincial People's Committee requested WHA Industrial Zone Nghe An Joint Stock Company to construct and raise the road of the industrial park. Assign Nghi Loc District People's Committee to continue to mobilize local people to agree on a technical solution to create synchronous infrastructure in WHA Industrial Zone Nghe An, to be completed before May 31, 2020.

After this deadline, if it is not possible to mobilize, the District People's Committee will have a plan to protect the construction before June 10, 2020. Assign the Southeast Economic Zone Management Board to complete the residential road before June 15, 2020, serving the travel needs of the people.

Regarding the drainage channel replacing Long Thuan canal: Assign Nghi Loc District People's Committee to complete site clearance for the section passing through 192 m2Nhan Hoa Parish cemetery land and 3 households along N5 road before June 30, 2020; in case of failure to ensure the progress of site clearance, causing flooding affecting people's lives and production, the District People's Committee must take responsibility. WHA Industrial Zone Nghe An Joint Stock Company focuses on constructing the cleared sections and coordinates with the District People's Committee during the construction process.

The Vice Chairman of the Provincial People's Committee also assigned the Southeast Economic Zone Management Board to complete the dossier proposing the exploitation of soil mines as materials for leveling the ground for projects in the economic zone and advise the Provincial People's Committee to submit a document to the Prime Minister for permission to change the purpose of protective forests to other purposes, and report to the Provincial People's Committee before May 31, 2020./.