Yen Xuan Bridge will be opened on National Day September 2
(Baonghean.vn) - On the afternoon of April 29, comradeLe Ngoc Hoa - PVice Chairman of the Provincial People's Committee worked with Hung Nguyen and Nam Dan districts and leaders of the General Corporation of Transport Works 4 to resolve problems regarding site clearance for the Yen Xuan bridge construction project.
![]() |
Comrade Le Ngoc Hoa inspected the construction site progress. |
Yen Xuan Bridge was started on October 2, 2015 with a total length of about 3.6 km, of which the bridge is 1.89 km long and the approach roads at both ends of the bridge are 1.40 km long. The total investment of the project is over 900 billion VND.
Up to this point, the units have achieved 56% of the workload. The bridge section from pier A1 to pier P20: completed 149/149 45x45cm reinforced concrete piles... The road section at the head of the bridge at pier A1 has completed the construction of 09 test piles of cement-reinforced soil piles, and is currently drilling experimental samples to deploy mass pile construction. Hung Nguyen bank intersection: Completed 08/14 right-of-way retaining wall blocks, completed 03/14 left-of-way retaining wall blocks.
![]() |
Completed P20 pillar top casting block |
On the Nam Dan bank, the road section at the head of the A2 pier has completed the K95 embankment for 600/1500m, reaching 19,387/53,763 m3.
After inspecting the site and listening to the progress report, comrade Le Ngoc Hoa acknowledged and highly appreciated the active coordination between the local government and the investor in implementing the project, especially the site clearance work. However, there are still some unresolved issues on both Hung Nguyen and Nam Dan sides.
Therefore, to ensure the pedestrian bridge is opened on July 20, inaugurated and put into use on the occasion of the upcoming National Day on September 2, comrade Le Ngoc Hoa requested the construction units to mobilize maximum human resources and modern machinery and equipment to speed up the construction progress of the project.
![]() |
Comrade Le Ngoc Hoa - Vice Chairman of the Provincial People's Committee requested the investor and contractor to speed up the construction progress to inaugurate the bridge on September 2, 2016. |
Investors need to continue to promote site clearance, promptly resolve difficulties and problems of local people, and promptly support affected projects. Regarding public roads, after the project is completed, local authorities need to make a document requesting investors to hand them over to people for use in the fields...