(Baonghean.vn) - On June 9, a working delegation from Nghe An province led by comrade Nguyen Dac Vinh - Member of the Party Central Committee, Secretary of the Provincial Party Committee, inspected the site of a number of key projects and works in the province.
Also attending were comrade Nguyen Xuan Duong - Deputy Secretary of the Provincial Party Committee, Chairman of the Provincial People's Committee; Vice Chairmen of the Provincial People's Committee: Huynh Thanh Dien, Hoang Viet Duong, Le Ngoc Hoa; leaders of provincial departments and branches and leaders of localities implementing works and projects.
During the 1-day period, the provincial leaders visited and surveyed key projects in the province, including: N5 road traffic project from Dong Nam Economic Zone to Hoa Son commune, Do Luong district; with a total length of 28.5km, with a total investment of 1,265 billion VND; Masan Group's food factory (Nam Cam Industrial Park); field survey at N2 road in Tho Loc Industrial Park (Dien Chau);... key projects in Hoang Mai town, Quynh Luu, Nghia Dan, Hung Nguyen, Cua Lo and Vinh city.
 |
Comrade Nguyen Dac Vinh inspected the site of the N5 road project connecting D4 and the N5 road resettlement area. This is the route serving the transportation of cement from Song Lam Cement Factory to Nghi Thiet Deepwater Port. |
 |
Visit the fish sauce production line of the Masan Food Industry Center invested by Masan Group in Nam Cam Industrial Park. When completed, the project will create about 1,000 jobs for workers and contribute about 3,000 billion VND to the budget in the next 10 years. |
 |
The provincial working group surveyed a 500m section of road connecting Dong Hoi Industrial Park and Nghi Son Economic Zone. This is a vital road, creating growth momentum for the Nam Thanh - Bac Nghe region. However, due to some problems, after many years of implementation, this section of road is still unfinished. |
 |
Leaving Hoang Mai Industrial Park, comrade Nguyen Dac Vinh and the working group continued to survey the road project to Tan Thang Cement Factory (Quynh Luu district). This route is 7 km long, serving cement transportation and local people's lives. |
 |
During the day, the delegation visited Nghia Dan MDF wood processing factory project. The project includes 2 lines of panel machines with a designed capacity of 12,000 m3/year, consumption capacity 30,000 m3/year and MDF factory has design capacity of 130,000 m3/year, consumption capacity 240,000 m3/year. The factory has started operating and the first products have been shipped and are highly appreciated by domestic and foreign customers. |
 |
Provincial leaders visited the clean vegetable production center of TH Group. |
 |
The Provincial Party Secretary congratulated and highly appreciated the success of TH Group in the field of high-tech agriculture. At the same time, he affirmed that the province will always accompany enterprises in this field. |
 |
Continuing the working trip, this afternoon, the provincial leaders visited the VSIP Nghe An Industrial, Urban and Service Complex. Currently, the site clearance work of the project has basically been completed and 1 enterprise has registered to invest. VSIP Nghe An is urgently constructing the factory section to call for more enterprises to invest. |
 |
Provincial leaders listened to the progress report of Yen Xuan Bridge Project. As planned, Yen Xuan Bridge will be closed on July 20 and the approach sections on the South and North banks will be urgently completed to organize the inauguration ceremony on the occasion of National Day, September 2. |
 |
Leaders of Cua Lo Port introduced the scale and capacity of loading and unloading goods through the port. |
 |
Visiting the North Canal Project, comrade Nguyen Dac Vinh requested the units to speed up the project progress to create a green, clean, beautiful and environmentally friendly appearance for Vinh City. |
Visiting and surveying key projects in the province, after listening to reports from units and localities on progress, scale as well as difficulties and obstacles of investors and construction units... Provincial Party Secretary Nguyen Dac Vinh thanked businesses for trusting and choosing Nghe An for investment. In response to investors' trust, he affirmed that the locality will continue to support and accompany businesses to effectively exploit land potential and advantages, develop the economy, contribute to solving jobs and increasing income for workers in the province.
Regarding the difficulties of enterprises, he pledged that the province will make efforts to discuss and find ways to resolve them, and at the same time direct relevant departments, branches and units to take drastic action, join hands with enterprises to speed up the progress of projects, and soon turn Nghe An into a province.center of finance, trade, tourism, education-training, science-technology, healthcare, culture, sports, and high-tech industry of the North Central regionin the spirit of Resolution 26 of the Politburo./.