(Baonghean.vn) - On the afternoon of December 23, 2021, authorized by the Northern Power Corporation, the Northern Power Construction Project Management Board and Nghe An Power Company successfully organized the acceptance, energized and put into operation the 110kV Hoang Mai 1 Transformer Station (E15.49).
Attending the ceremony, on behalf of the electricity industry, there was comrade Bang Hong Hien - Director.Nghe An Electricity Company; Deputy Directors and leaders of departments of Nghe An Electricity Company; representatives of the Northern Power Project Management Board. On the side of Hoang Mai Town, there were comrade Le Truong Giang - Secretary of Hoang Mai Town Party Committee and leaders of departments, branches and sectors of the Town.
![]() |
Mr. Le Quang Thanh - Deputy Director of Nghe An Electricity Company spoke at the energization ceremony. |
The 110kV Hoang Mai 1 Transformer Station and branch project is built in Quynh Thien ward - Hoang Mai town, Nghe An province, with a total usable area of 4450 m2, equipment is installed according to a segmented busbar diagram including 01 transformer T1 bay (110/35/22kV), 02 110kV line bays connected by a communication bay.
The 110kV equipment is installed outdoors with a planned capacity of 02 63 MVA transformers. The 22kV side uses a diagram of a busbar system with segments using indoor cabinets, the station is built according to the criteria of a remote control substation; Building an information system, SCADA connecting to the Nghe An province remote control center, A1 and EVNNPC data center according to the criteria of an unmanned station.
![]() |
Workers perform voltage circuit checks before energizing. |
![]() |
Workers operate the equipment. |
Hoang Mai 1 110kV transformer station is built with 08 22kV feeder bays to supply electricity to Hoang Mai 1 industrial park and neighboring loads of Hoang Mai town center.
Due to the impact of the Covid-19 pandemic, the construction work encountered many difficulties. However, with the determination of Nghe An Power Company, the Northern Power Construction Project Management Board and contractors have strictly controlled the construction time to complete the project on schedule and well implemented Covid-19 epidemic prevention work at the construction site.
![]() |
Local government leaders, leaders of the Northern Power Construction Project Management Board and leaders of Nghe An Power Company at the power energization ceremony. |
The completion of the 110kV Hoang Mai 1 transformer station is of great significance, contributing to the timely supply of electricity to the Hoang Mai 1 industrial park load, one of the key projects of Nghe An province in 2021 and neighboring loads. At the same time, when energized, the project will strengthen the grid connection, improve the stability and reliability of power supply, minimize power loss and improve voltage quality for the distribution grid of Hoang Mai town in particular and Nghe An province in general.