Dien Chau district will organize protection for the construction of Dien Doai overpass over the North-South expressway.
(Baonghean.vn) - With the goal of ensuring safety during the construction of the Dien Doai overpass on National Highway 48 over the North-South Expressway, Nghi Son - Dien Chau section, the People's Committee of Dien Chau district has just approved a plan to organize construction protection.
It is expected that construction security will be organized in the coming days.
The reason why the People's Committee of Dien Chau district organized to protect the construction of Dien Doai overpass over the North-South expressway is because recently, 14 households with land along National Highway 48 have carried out some acts of obstructing the construction (hanging protest banners, gathering construction materials within the construction area). These acts led to the households believing that the construction of Dien Doai overpass on National Highway 48 over the North-South expressway would devalue their land, and they requested compensation or resettlement.

However, according to the Land Clearance Council of Dien Chau district, the request of the 14 households is baseless. Because, in the previous phase, when upgrading National Highway 48, the households received compensation, the traffic safety corridor of National Highway 48 was marked at the site; meanwhile, the Dien Doai overpass over the North-South Expressway is located entirely on the main axis and within the corridor of National Highway 48, not encroaching on the land of the related households.
To facilitate households with land adjacent to National Highway 48 mentioned above, Project Management Board 6 - Ministry of Transport has adjusted the approach road to the western end of the M1 bridge, combined with adding a left-of-route service road through 14 land plots of households (service road scale: 4.5m wide roadbed, 3.5m wide asphalt surface, class B road scale).

At the conference to deploy the construction protection plan held on June 30, 2023, Chairman of Dien Chau District People's Committee Tang Van Luyen said that regarding the recommendations of the households, Dien Chau District People's Committee and the District Site Clearance Council have proactively researched and sought opinions from provincial and central agencies to respond in writing to the households many times. As for the recommendations of the households regarding the safety range of the bridge, on June 7, 2023, the Ministry of Transport also issued Document No. 5888/BGTVT-KCHT to the District People's Committee and the Provincial People's Committee. According to the Ministry of Transport, the safety corridor limit of the Dien Doai overpass section at Km414+208 (expressway route) is currently within the safety corridor of National Highway 48, which has been marked at the site according to the Minutes of Handover to Dien Doai Commune and Dien Yen Commune on October 10, 2016.

In addition, the People's Committee, the District Compensation and Site Clearance Council, and the People's Committee of Dien Doai Commune also spent a lot of time in dialogue, explaining legal regulations; propagating and mobilizing households not to obstruct the construction of the project. Right before the conference, on the afternoon of June 29, the District People's Committee also organized a dialogue with representatives of 14 households under the chairmanship of the Chairman and Vice Chairman of the District People's Committee.
Regarding the Nghi Son - Dien Chau Expressway Construction Investment Component Project under the North - South Eastern Expressway Construction Investment Project in the 2017-2020 period, this is a national key project. According to the assigned schedule, the XL03 package (section Km405+00 to Km419+600 in the districts of Quynh Luu, Dien Chau, Yen Thanh) must be completed before July 21, 2023, and is expected to be technically opened to traffic on September 2, 2023 as directed by the Prime Minister. Therefore, to ensure progress, the People's Committee of Dien Chau district will organize the protection of the construction of the Dien Doai Overpass on National Highway 48 over the North - South Expressway, Nghi Son - Dien Chau section.
The time for the People's Committee of Dien Chau district to organize construction protection will begin in the coming days, expected to last until September 1, 2023 - before the technical traffic opening time according to the construction unit's plan.
The set objective is to ensure the safety of the construction of the Dien Doai viaduct on National Highway 48 over the North-South expressway at the location west of pier M1 and the left-side service road; ensure the construction of the project according to the approved design and the progress of the project to build some expressway sections on the North-South Eastern route in the period of 2017-2020 (in Dien Doai commune, Dien Chau district); minimize damage and loss of property, and prevent acts of obstruction that affect the construction, causing insecurity and disorder in the area...