Working through holidays, Vinh city basically cleared the Vinh - Cua Lo road

Pearl DNUM_ACZAFZCABJ 09:05

(Baonghean.vn) - Working continuously during all holidays of April 30 and May 1, departments and the Vinh City Land Fund Center have mobilized to liberate more than 70 out of 126 households in Nghi Duc, Vinh City to hand over the site to the construction unit of the Vinh - Cua Lo road.

Continuously during the recent holidays, many departments and the Vinh City Land Fund Development Center in conjunction with Nghi Duc Commune have focused on clearing the land on Vinh - Cua Lo road through Nghi Duc. Photo: The delegations went to each family to mobilize. Photo: Tran Chau

The Vinh - Cua Lo route through Vinh city is 3.4km long, and has been allocated capital but is stuck in site clearance because the state's compensation price, according to the people, is lower than other projects. With high determination and many resolute measures, Vinh city has directed the clearance of the entire route from April to the end of June 2019. Photo: Tran Chau

Mr. Pham Thanh Tinh's family in Xuan Dong hamlet, Nghi Duc commune is a retired soldier. His house and land had to be relocated. On the afternoon of May 1, the family handed over the site to the Transport Project Management Board. Photo: Tran Chau

In just 4 days off from May 27 to 1, 2019, nearly 70/126 Nghi Duc households (subject to site clearance) handed over their sites and voluntarily cleared their houses to the construction party. Nghi Duc commune officials also came out to help people dismantle their houses. Photo: Tran Chau

Mr. Ha Thanh Tinh - Vice Chairman of the City People's Committee said that the Vinh - Cua Lo road through Vinh city is 3.4 km long, the total number of households to be cleared is 198 households, of which 126 households are in Nghi Duc. Implementing the province's direction to hand over the site on April 30, in the past time, the city has focused on ensuring the set progress. Thanks to the synchronous implementation of many solutions, currently most households in Nghi Duc have agreed and committed to hand over the site and receive resettlement land. Photo: The green areas on the route show that the site has been cleared. Photo: Tran Chau

People in Nghi Duc commune, Vinh city actively dismantle their houses. Photo: Tran Chau
Motorbikes are ready to assemble to construct the road when people evacuate. Currently, the Department of Transport is directing contractors to focus on implementing construction of sections with available land, coordinating with localities to clear remaining sections for early handover, ensuring construction of layer 1 asphalt concrete as required. Photo: Tran Chau

95m Vinh - Cua Lo road through Nghi Duc, Vinh city. Graphics: Lam Tung