Nghe An needs 2,000 billion VND to invest in upgrading the rural power grid

DNUM_BHZBCZCABF 14:33

(Baonghean.vn) - Currently, in the province, there are 439 communes, Nghe An Electricity Company has received and sold electricity to households in 421 communes and some residential areas. The cumulative received volume is 10,272 km of 0.4kV line; 674,426 households use 1-phase electricity and 25,392 households use 3-phase electricity. Total received value: 425 billion VND.

trạm biến áp chống quá tải

After receiving, EVN and NPC have been interested in investing in a number of projects such as the KFW project.(Total investment: 746,232 billion VND) put into operation,cThe restoration of 23% (2693.31/11,600 km of low voltage grid) with a scale of over 274 communes has initially shown some improvements in terms of safety for this grid system in terms of reducing losses and improving power quality.In Yen Thanh, in 2015, 15 billion VND was invested to upgrade the rural power grid. (In the photo: The overload prevention transformer station for Do Thanh 2 station worth 1.4 billion VND in Dong Thi hamlet, Do Thanh has just been invested from Nghe An electricity budget).

Thợ điện xóm Phú Vinh, Đô Thành kiểm tra lưới điện
Yen Thanh is the locality with the third largest number of customers in the province. Currently, Yen Thanh electricity branch is managing over 81,000 customers. After the handover, the quality of electricity in many communes has been improved. In the photo:Electrician of Phu Vinh hamlet, Do Thanh checks the power grid.
Tại Diễn Châu, chi nhánh điện Diễn Châu hiện đang quản lý 600km đường dây hạ thế. Năm 2015 được đẩu tư 29 tỷ đồng để đầu tư 7 trạm biến áp, đường dây trung áp; 101 km đường dây hạ áp
In Dien Chau, Dien Chau Electricity Branch is currently managing 600km of low voltage lines. In 2015, from a budget of 29 billion VND, 7 transformer stations, medium voltage lines; 101km of low voltage lines...
1
However, the investment in upgrading has not yet met the requirements. There are still many substandard columns, many low concrete columns cast by local people, and many bamboo and wooden columns that do not ensure safe operation.According to Nghe An Electricity Company, the low voltage grid still needs to be renovated up to 7,894.557 km. It is estimated that 2,000 billion VND is needed to invest in renovation, wire replacement and investment in about 600 transformer stations to improve power quality and reduce power loss.(Photo taken on December 15 in Dien Dong, Dien Chau).

Thu Huyen - Thanh Quynh