Nghi Loc is about to complete the main road along the center of Quan Hanh town.

Nguyen Hai DNUM_AIZADZCACD 08:03

(Baonghean.vn) - The vertical road project of Quan Hanh town center (Nghi Loc) has its starting point from National Highway 48E in Quan Hanh town to Nghi Trung commune, with a length of 2.37 km, and is one of the key urban infrastructure projects of Nghi Loc.

According to the Nghi Loc District Investment Project Management Board, the projectVertical road of Quan Hanh town centerThe total investment is 135,106 billion VND, approved in 2016 from the central budget. The project is divided into 2 phases, of which phase 1 is 68,916 billion VND and phase 2 is 66,190 billion VND.

Construction unit completes sidewalks, lighting and roads connecting to residential roads. Photo: Nguyen Hai

Although approved in 2016, it was not until the end of the term, 2019, that 10 billion VND was allocated, so construction had to begin in 2020 after additional capital was allocated.

After completing a length of about 350m, due to many arising problems and lack of funding, the project was stopped. By September 2022, the project was allocated over 80 billion VND, but due to compensation, site clearance and resettlement issues, only over 60 billion VND could be constructed, and the remaining 18.4 billion VND had to be extended and carried over to 2023.

The road waiting to connect with the National Highway 48E intersection from the town to Son market (Nghi Loc). Photo: Nguyen Hai

Therefore, in 2023, along with the procedures for requesting an extension, Nghi Loc district is applying for a connection of this road axis withNational Highway 48E; submit additional planning for 19 land lots to resettle households and organize site clearance for the road section passing through the headquarters of the District Social Policy Bank.

The road running through the side of the Nghi Loc District Social Policy Bank is waiting for procedures to adjust and supplement the new planning to hand over the site for the project. Photo: Nguyen Hai

Mr. Le Van Duc - Director of Nghi Loc Infrastructure Investment and Development Project Management Board said: Although the investment source is arranged slowly and the implementation process has some problems that have caused the construction to be prolonged, basically up to this point, the main items such as sidewalks, drainage ditches, and trees have been basically completed and the road surface is being paved, with an estimated construction value of 87%.

The construction unit is paving the road in the northern section. Photo: Nguyen Hai

After many missed deadlines due to problems, recently, the biggest bottleneck is the intersection between the vertical axis of Quan Hanh town center and the provincial road from National Highway 1A to Nghi Dien, which has been compensated and cleared. If the source extension procedure is approved, the project will be completed and put into use in 2023, thereby creating a new highlight for the town.

(Mr. Le Van Duc - Director of Nghi Loc Investment Project Management Board)