Efforts to overcome storm consequences at Vissai international port Nghe An

Quang An September 30, 2025 15:17

More than 500 meters of ramps, conveyor belts, and canopies at Terminal 2 of Vissai Nghe An International Port were damaged by storm No. 10. Currently, the unit is planning to transfer the entire volume to Terminal 1, determined to maintain the supply chain.

Clip: Quang An
bna_1.jpg
Vissai Nghe An International Seaport is one of the province's important seaports, serving as a gateway for trade in the North Central region, serving the export of cement and general goods, contributing to promoting the marine economy. However, after storm No. 10, the port was severely damaged. Photo: Quang An
bna_4.jpg
According to the reporter's records on the morning of September 30, the approach bridge at wharf No. 2, about 2km long, had a series of damaged spots after the storm, of which more than 500 meters were the most severely damaged, causing temporary suspension of transportation activities. Photo: Quang An
bna_3a.jpg
A section of the bridge leading to the crane area was destroyed by the storm, completely cutting off the supply of goods. Photo: Quang An
bna_2.jpg
The conveyor system was damaged. It is known that previously, wharf number 2 at the port was responsible for exporting about 15,000 tons of goods per day. Photo: Quang An
bna_5a.jpg
Many conveyor belts could not withstand the strong winds and constant shaking after storm No. 10. Photo: Quang An
bna_3.jpg
Some technical items have not been able to be restored after the storm. According to Mr. Nguyen Quoc Tai - Director of Vissai Nghe An International Port, this is the most destructive storm in many years. Although the Port has implemented prevention plans in advance, it is still heavily affected at wharf No. 2. Photo: Quang An
bna_sa.jpg
The road surface of the approach bridge is peeling off, currently only motorbikes can pass through this area. Photo: Quang An
bna_10.jpg
Many conveyor belts and roofs were washed into the sea. Photo: Quang An
bna_12.jpg
According to the leader of Vissai International Port, repairing wharf No. 2 will take about 6 months, however, the unit will have solutions to ensure the flow of goods is not interrupted. Photo: Quang An
bna_8(1).jpg
In the event that wharf No. 2 has to temporarily stop operations, port leaders have come up with a plan to transfer all cargo volume to wharf No. 1. This means that the system of bridges, conveyor belts, roads, and roofs at wharf No. 1 must bear a larger capacity to meet customer demands in the coming time. Photo: Quang An