Standing Vice Chairman of the Provincial People's Committee inspected the 500kV line 3 project
Standing Vice Chairman of the Provincial People's Committee Le Hong Vinh acknowledged and highly appreciated the efforts of the contractor and workers. At the same time, he hoped that the units would continue to focus on ensuring that the 500kV line 3 project is completed on schedule.
On the afternoon of July 31, a working delegation led by comrade Le Hong Vinh - Member of the Provincial Party Committee Standing Committee, Permanent Vice Chairman of the Provincial People's Committee inspected the 500kV transmission line project through Nghe An. Accompanying comrades were: Nguyen Nhu Khoi - Member of the Provincial Party Committee, Vice Chairman of the Provincial People's Council; Pham Van Hoa - Director of the Department of Industry and Trade; Tran Minh Ngoc - Chairman of the Nghe An Provincial Journalists Association, Director of Nghe An Radio and Television Station and representatives of departments, branches and sectors.
.jpg)
The 500kV 3-circuit line project through Nghe An province has a total length of nearly 100km with 202 pole foundation locations and 88 anchorages. It includes 2 component projects: the 500kV Quang Trach - Quynh Luu line, approximately 82.33km long, 168 pole foundation locations, and the 500kV Quynh Luu - Thanh Hoa line, approximately 17.5km long, 34 pole foundation locations. This is a key, urgent project, playing a particularly important role in national energy security.
-c532520c62e1d5d4a731cf7c8b614d07.jpg)
According to the report of the Department of Industry and Trade, as of July 31, the foundation and column erection work has completed 202/202 foundation positions. The column section has completed 175 column positions; 27 column positions are being erected. Basically, the column erection on the route is mainly done by hand combined with machines.
.jpg)
For the wire pulling part, Quang Trach - Quynh Luu project is pulling 19 anchors, has completed 10 anchors. Quynh Luu - Thanh Hoa project is pulling 5 anchors, has completed 1 anchor.
The working group directly inspected the site at column number 460, Ngoc Son commune, Quynh Luu district. The column was handed over on July 27, 2024, column type 2xN511-84C, weighing 300 tons. Currently, the main body 1 has been basically assembled to form the column, anti-torsion braces are being installed, bolts are being tightened, and the column is being completed. The main body 2 is currently erecting the 4th floor (40/84m). This column is expected to be completed before August 5, 2024.
.jpg)
Next, the working group also inspected the anchorage at position 453-455 in Ngoc Son commune, Quynh Luu district. This anchorage has a length of 907m, expected to be completed before August 6, 2024.
At the site, representatives of contractors said they were mobilizing vehicles, materials, machinery, and construction workers to ensure progress. Local leaders also reported on the work of clearing the ground for column foundations and power grid corridors to serve the construction.
.jpg)
Standing Vice Chairman of the Provincial People's Committee Le Hong Vinh directly presented gifts to encourage workers and laborers working at the construction site; acknowledged and highly appreciated the efforts of the contractor and workers to closely follow the set plan.
In the coming time, comrade Le Hong Vinh requested the construction unit to allocate sufficient resources to speed up the construction progress, striving to complete the project on schedule as required by the Prime Minister. The construction units prepare plans to respond to extreme weather, ensuring the safety of people, works, machinery and equipment at the construction site.