Law

Will enforce and reclaim 659.6m2 of land from households in Van Yen hamlet, Hoa Son commune (Do Luong) to implement the project to renovate and upgrade National Highway 7

PV Group DNUM_CJZAIZCACE 13:30

The section Km24+628.81 - Km24+1051.21 of National Highway 7 through Van Yen hamlet, Hoa Son commune (Do Luong) has a length of 422.4m and is within the scope of the National Highway 7 Renovation and Upgrade Project. The Vietnam Road Administration approved the adjusted construction drawing design in Decision No. 4654/QD-CDBVN dated November 7, 2023. However, the construction work has been delayed for a long time due to problems in site clearance.

The Ministry of Transport issued Decision No. 333/QD-BGTVT nMarch 18, 2022,approved the project to upgrade National Highway 7, section Km0 - Km36, and handle landslides caused by storms and floods in the Khe Thoi - Nam Can section, Nghe An province. Accordingly, the project will be completed in 2024.

Trong ảnh là Quốc lộ 7, đoạn Km24+628,81 – Km24+1051,21 đi qua xóm Vạn Yên, xã Hòa Sơn, huyện Đô Lương.
In the photo is National Highway 7, section Km24+628.81 - Km24+1051.21 passing through Van Yen hamlet, Hoa Son commune, Do Luong district on August 27, 2024. The image shows that this section of National Highway 7 according to the new design has not been connected. Photo: PV
z5774124325625_369c68638666a9d5626b886cc51d4416.jpg
The section Km24+628.81 – Km24+1051.21 of the old National Highway 7 (still existing and in use) is steep and winding. Implementing the National Highway 7 Renovation and Upgrade Project according to Decision No. 333/QD-BGTVT, this section will be straightened, ensuring safety for people and vehicles when participating in traffic. The design and construction drawing adjustment of the section Km24+628.81 – Km24+1051.21 was approved by the Vietnam Road Administration on November 7, 2023, in Decision No. 4654/QD-CDBVN. Photo: PV

Quyết định số 4654/QĐ-CĐBVN ngày 7/11/2023 của Cục Đường bộ Việt Nam phê duyệt thiết kế bản vẽ thi công điều chỉnh đoạn Km24+628,81 – Km24+1051,21 của Quốc lộ 7 qua xóm Vạn Yên, xã Hòa Sơn (Đô Lương), và bản đồ đo đạc thửa đất của hộ gia đình còn có vướng mắc trong công tác giải phóng mặt bằng.
Decision No. 4654/QD-CDBVN dated November 7, 2023 of the Vietnam Road Administration approving the design of the adjusted construction drawing of the section Km24+628.81 - Km24+1051.21 of National Highway 7 through Van Yen hamlet, Hoa Son commune (Do Luong); and the land measurement map of the household that still has problems in site clearance. Photo: PV
Đoạn Km24+628,81 – Km24+1051,21 củ Quốc lộ 7 qua xóm Vạn Yên, xã Hòa Sơn (Đô Lương)
The section Km24+628.81 – Km24+1051.21 of National Highway 7 through Van Yen hamlet, Hoa Son commune (Do Luong) is only 422.4m long, however, up to now, only 3/4 of the construction has been completed, there are still more than 100m that cannot be constructed because a household still has problems and does not coordinate with State agencies to carry out procedures for land acquisition and site clearance. Photo: PV
z5775840403084_91a1fe2b1e2a5d4be2ee54b05b274e9a.jpg
National Highway 7, section Km24+628.81 – Km24+1051.21 seen from the Transport Cemetery towards Do Luong district. Photo: PV
Hiện trạng đoạn Km24+628,81 – Km24+1051,21 của Quốc lộ 7 (từ huyện Đô Lương hướng Đông)
The current status of the section Km24+628.81 – Km24+1051.21 of National Highway 7 (standing from Do Luong district towards the East) is unfinished and cannot be connected due to problems in site clearance. Photo: PV
Tại Quyết định số 4654/QĐ-CĐBVN ngày 7/11/2023 của Cục Đường bộ Việt Nam nêu rõ, đoạn Km24+628,81 – Km24+1051,21 của Quốc lộ 7 được điều chỉnh tim tuyến về trái tuyến với phạm vi điều chỉnh từ 0m - 9,80m
Decision No. 4654/QD-CDBVN clearly states: "Adjust the centerline of the section Km24+628.81 - Km24+1051.21 to the opposite direction with an adjustment range of 0m - 9.80m to avoid house demolition and resettlement for households living in the section, speeding up the project's site clearance progress". In the photo, an officer of the Do Luong District People's Committee guides the land acquisition scope of a household in Van Yen hamlet, Hoa Son commune to implement the National Highway 7 upgrading project, section Km24+628.81 - Km24+1051.21. Photo: PV
z5774124242053_a52d7f5bb66b64791eafb716b7f80b7c.jpg
The land plot with a family still having problems in Van Yen hamlet, Hoa Son commune, Do Luong district has a total area of ​​over 1,660m2.2Based on the construction drawing design approved by the Vietnam Road Administration in Decision No. 4654/QD-CDBVN, the District People's Committee will have to reclaim 659.6m2to hand over to the investor to complete the project. Photo: PV
z5774123989101_7f417eebf3c60b9466d4b2b93fa7ed3f.jpg
National Highway 7 is an important arterial road not only for Nghe An province but also for the country, so the implementation of the National Highway 7 Renovation and Upgrade Project is extremely important. However, the project's progress is too slow compared to the set plan. Due to the slow progress, the Ministry of Transport has repeatedly issued official dispatches reminding and urging (on August 23, 2024, the Ministry of Transport continued to issue Official Dispatch No. 9178/BGTVT-CQLXD requesting the Vietnam Road Administration to remove obstacles in site clearance, and to ensure the quality and progress of the National Highway 7 Renovation and Upgrade Project). Therefore, in order for the section Km24+628.81 - Km24+1051.21 of National Highway 7 to be completed, the People's Committee of Do Luong district has issued a decision and developed a plan to enforce land recovery for households in Van Yen hamlet, Hoa Son commune. According to the People's Committee of Do Luong district, the plan to enforce land recovery according to Decision No. 2287/QD-UBND dated July 31, 2024 will be implemented in September 2024. Photo: PV

Featured Nghe An Newspaper

Latest

x
Will enforce and reclaim 659.6m2 of land from households in Van Yen hamlet, Hoa Son commune (Do Luong) to implement the project to renovate and upgrade National Highway 7
POWERED BYONECMS- A PRODUCT OFNEKO