Tan Ky forcibly reclaimed land to implement the project of building a waste treatment plant.
(Baonghean.vn) - On the morning of October 13, the People's Committee of Tan Ky district applied compulsory measures to recover land from the family of Mr. Nguyen Hong Thai and Ms. Hoang Thi Hoa in Ho Thanh hamlet, Tan Long commune to implement the project to build a solid and liquid waste treatment plant.
![]() |
On the morning of October 13, Tan Ky district applied compulsory measures to recover land from Mr. Nguyen Hong Thai's family in Ho Thanh hamlet, Tan Long commune. Photo: Xuan Hoang |
Faced with the urgent situation of solid and liquid waste treatment in the locality, on November 17, 2020, the Provincial People's Committee approved the policy of building a solid and liquid waste treatment plant project.Tan Kyin Tan Long commune, with a planning area of over 33,492m2, total project capital 158 billion VND. Factory construction area in Valley 70 of Tan Long commune.
Of this planned area, more than 33,333m2is perennial crop land, 5% public land managed by Tan Long Commune People's Committee, has been assigned to 4 households for production. The remaining area is more than 159m2managed by Tan Long Commune People's Committee.
![]() |
The area of land forcibly acquired is an acacia forest that is ready for harvest. Photo: Xuan Hoang |
Accordingly, Tan Ky District People's Committee has a plan for compensation and support for site clearance according to State regulations to implement the Factory Construction Investment Project.solid and liquid waste treatmentin Tan Ky district for the recovered land area of more than 33,492m2is more than 2,117 billion VND. This compensation and site clearance support plan has been approved by the Provincial People's Committee.
However, among the 4 families, there is 1 family, Mr. Nguyen Hong Thai and Ms. Hoang Thi Hoa, who refused to hand over more than 21 thousand m2for the district to implement the project.
![]() |
Forces on duty to reclaim land. Photo: Xuan Hoang |
Therefore, implementing Decision No. 3515/QD-UBND on compulsory land recovery of Tan Ky District People's Committee, on the morning of October 13, the competent authorities of Tan Ky District applied measures.coerciveLand recovery for the family of Mr. Nguyen Hong Thai and Ms. Hoang Thi Hoa in Ho Thanh hamlet, Tan Long commune to carry out the project of building a solid and liquid waste treatment plant.
![]() |
The project to build a solid and liquid waste treatment plant for Tan Ky district was approved by the Provincial People's Committee for the Valley 70 area of Tan Long commune. Photo: Xuan Hoang |
The time for implementing this land recovery enforcement is 15 days after the date this decision is delivered to the family of Mr. Nguyen Hong Thai and Ms. Hoang Thi Hoa; posted according to regulations, but the family of Mr. Nguyen Hong Thai and Ms. Hoang Thi Hoa still does not voluntarily recover the assets on the land and hand over the premises to the competent State agency./.