Cua Lo Town proposes to withdraw 6 slow-moving projects

PV Group DNUM_BFZBBZCABJ 11:10

(Baonghean.vn) - Cua Lo Town has just reported on the progress of investment projects that have been inspected, extended, and adjusted from 2012 to 2019. Accordingly, it proposed to revoke 6 slow-moving projects.

According to the review of the People's Committee of Cua Lo town on 14 projects that have been extended by the Provincial People's Committee over the past many years, by November 2019, only 3 projects were completed, the remaining many projects were not implemented or progressed slowly.

Report on projects that have been inspected, extended and adjusted from 2012 to present by the People's Committee of Cua Lo town. Photo: PV

Cua Lo Town People's Committee proposed to withdraw 6 projects including:

1.Project: Wharf and fishing port:

The investor is Ha Dung Company Limited, the construction planning location: Nghi Hai ward - Cua Lo town. The project has a total planning area of ​​location 1: 14,791.0m2; position 2: 14,642.7 m2.

Scale of 1 wharf port and 01 expanded inshore fishing port and auxiliary works. Total investment of 94,642,151,039 VND.

The project of the wharf and fishing port invested by Ha Dung Company Limited is behind schedule. Photo: Tran Chau

The project was approved in Decision No. 1941/QD.UBND-CN dated May 26, 2008 of Nghe An Provincial People's Committee on approving the detailed planning for the construction of the wharf and fishing port in Nghi Hai Ward, Cua Lo Town. However, at location 2, the unit implemented a number of items that were not in accordance with the approved planning. At location 1, the unit has not yet invested in any construction works according to the approved detailed planning.

The project has now expired (the progress is allowed to be extended until September 1, 2019 in Decision No. 4161/QD-UBND dated September 11, 2017 of Nghe An Provincial People's Committee).

Some long-standing unfinished projects have ruined the beauty of the coastal urban area of ​​Cua Lo. Photo: PV

2.Project: Luxury apartment and villa complex combined with commercial services

The project is invested by Hanoi Construction Joint Stock Company No. 3. The implementation location is in Nghi Huong ward, Cua Lo town, Nghe An province. In 2009, the land use area of ​​the project was 8,047.74m2.2, in which construction area: 5,691.55m2The project has a scale of 1 commercial apartment building 17 floors high and 12 villas.

The project has now expired (September 1, 2019), but the project has only completed some raw villas and has not yet implemented high-rise apartments.

3. Commercial and service land projectsby79 Tourism Service Trading Joint Stock Company is the investor in Nghi Huong ward, Cua Lo town, Nghe An province.

Project area: 2,129.4m2, licensed in 2011. After 8 years, the project has not yet been implemented.

4. Psychological counseling and physiotherapy project.The investor is the Center for Counseling and Psychotherapy.

Location: Nghi Huong ward, Cua Lo town, Nghe An province. Area: 3174.3m2.

Scale: 5-storey nursing home and auxiliary items.

The project was extended to September 1, 2019 in Decision No. 4161/QD-UBND dated September 11, 2017 of Nghe An Provincial People's Committee, but until now, only the fence surrounding the land has been built.

5.Elderly Care Center Project.This project is invested by Nghe An Elderly Care Center. Location: Nghi Hoa ward, Cua Lo, area: 5,260.7m2.

The project has a scale of 01 2-storey management house, 02 2-storey resorts, 01 3-storey resort, 01 5-storey resort, 01 2-storey service house, 01 1-storey memorial and funeral house and auxiliary items.

The project was extended to complete the project until September 1, 2019, but so far only a 2-storey resort has been built.

6. Project of the Operation Center of the Vietnam - Laos - Cambodia Economic Cooperation Development Association.Investor: Vietnam - Laos - Cambodia Economic Development Association. Location: Nghi Hoa, Cua Lo Town, Nghe An Province. The project was licensed in 2011. However, up to now, no construction items have been implemented.

The hotel and motel area of ​​Song Hong Tourism Joint Stock Company is still unfinished. Photo: PV

Chart of delayed projects in Cua Lo Town as of November 2019. Graphics: Lam Tung