Compensation for land clearance on National Highway 1A through Nghe An must be paid before May 31.

Tien Dong DNUM_CGZADZCACF 16:41

That was the request of comrade Hoang Phu Hien - Member of the Provincial Party Executive Committee, Vice Chairman of Nghe An Provincial People's Committee to localities at the meeting to discuss solutions to remove difficulties and obstacles in compensation and disbursement of additional funding for the project to upgrade and expand National Highway 1A, held on the afternoon of March 26.

bna_toancanh.jpg
Overview of the meeting. Photo: Tien Dong

According to the report of the Department of Construction, since the Provincial People's Committee allocated 1,275 billion VND to districts and towns to settle compensation for site clearance (including delayed payment) of the National Highway 1A expansion projects through Nghe An province, the central budget tasks have arisen after these projects have been finalized.

Although the Provincial People's Committee and departments and branches have issued 283 documents directing the handling and removal of obstacles in the settlement of petitions, funding, and compensation plans for site clearance; of which the Provincial People's Committee alone has issued 108 documents of various types; the districts have also actively participated in disbursing funds according to schedule. However, due to many difficulties and obstacles, the payment is still slow.

Hiện tại Đoàn kiểm tra của huyện Quỳnh Lưu đang tiến hành rà soát lại. Ảnh: Tiến Đông
National Highway 1A through Cau Giat town (Quynh Luu). Photo: Tien Dong

According to the presentation of local representatives, the most difficult problem at present is that the records and documents are incomplete; the assignment of ownership of many plots of land is difficult; there are no maps to determine boundary markers; not to mention that many localities have also received a number of petitions from new land users or previous land users due to disputes...

Therefore, up to this point, localities have only disbursed 596.912 billion VND/1,275 billion VND allocated (46.8%), of which: Hoang Mai Town: 149.6 billion VND; Quynh Luu 96.128 billion; Dien Chau 345.618 billion; Vinh City 5.566 billion; the remaining 678.088 billion VND has not been disbursed.

bna_luyen.jpg
Mr. Tang Van Luyen - Chairman of Dien Chau District People's Committee presented the difficulties in paying compensation for land acquisition and clearance for National Highway 1A through Dien Chau District. Photo: Tien Dong

At this meeting, localities continued to recommend the Provincial People's Committee to direct relevant departments and branches to provide guidance to resolve problems in cases of missing records and documents; appraise records, approve additional extracts and measurements for cases that localities have submitted.

bna_dung.jpg
Mr. Ho Viet Dung - Deputy Director of the Department of Finance spoke at the meeting. Photo: Tien Dong

In particular, in the context of implementing the policy of not organizing district-level government according to Conclusion 127-KL/TW of the Politburo, if the payment is not completed as soon as possible, it will be very difficult when this task has to be assigned to the communes later.

Hoàng Phú Hiền
Vice Chairman of the Provincial People's Committee Hoang Phu Hien concluded at the meeting. Photo: Tien Dong

Concluding the meeting, Mr. Hoang Phu Hien - Vice Chairman of the Provincial People's Committee requested localities to promptly pay for cases where there has been a decision to approve the compensation plan; at the same time, requested localities to report and continuously update the progress to the Provincial People's Committee; carefully review, not to miss any subjects and require localities to have a commitment to these figures, to avoid petitions and complaints later.

Comrade Hoang Phu Hien also requested that localities complete compensation payments before May 31, 2025.