Thanh Duy DNUM_BCZAHZCACE 13:32

On the morning of July 12, comrade Thai Thanh Quy - Member of the Party Central Committee, Secretary of the Provincial Party Committee, Chairman of the Provincial People's Council, Head of the National Assembly Delegation of Nghe An province directly went to the construction site of pole positions in Dien Chau and Yen Thanh districts to inspect and urge the progress; encourage cadres and workers who are constructing the 500kV project, circuit 3, through Nghe An.

bna_img_1556.jpg
Nghe An Provincial Party Secretary Thai Thanh Quy and the working delegation inspected the construction progress of VT 409 pole in Dien Thai commune, Dien Chau district to serve the wire pulling. Photo: Thanh Duy

Accompanying the delegation were comrades: Nguyen Dinh Hung - Member of the Provincial Party Committee, Chief of the Provincial Party Committee Office; Hoang Quoc Viet - Member of the Provincial Party Committee, Director of the Department of Natural Resources and Environment; Pham Van Hoa - Director of the Department of Industry and Trade; and leaders of relevant localities.

The 500kV line project, circuit 3 from Quang Trach (Quang Binh) to Pho Noi (Hung Yen) is a national key project, large-scale with a length of about 519 km double circuit passing through 9 provinces, of which nearly 100 km passes through Nghe An province with 2 component projects: Quang Trach - Quynh Luu and Quynh Luu - Thanh Hoa.

bna_img_1447.jpg
Comrade Thai Thanh Quy - Secretary of Nghe An Provincial Party Committee discussed and encouraged engineers, workers and union members and youths at the VT 409 pole location in Dien Thai commune, Dien Chau district to serve the wire pulling. Photo: Thanh Duy

Thoroughly implementing the Prime Minister's guiding principle, "wires do not wait for poles, poles do not wait for foundations, foundations cannot be done by just one person", Nghe An provincial leaders have focused on directing relevant levels, sectors and localities to coordinate with investors and construction units to synchronously deploy the work, which has been basically completed so far.

Nghe An has handed over the entire area of ​​column foundations (202/202) and the entire corridor of the route (203/203 column spaces, 88/88 anchor spaces).

bna_img_1357.jpg
The coil of electric wire has been transported to the location of VT 409 pole in Dien Thai commune, Dien Chau district to serve the wire pulling. Photo: Thanh Duy

In the province, there are 53 households affected by land acquisition for project implementation (Nam Dan district: 19 households, Nghi Loc district: 9 households, Yen Thanh district: 2 households, Dien Chau district: 19 households, Hoang Mai town: 4 households), of which 18 households requested resettlement land allocation (Nam Dan district: 1 household, Nghi Loc district: 5 households, Dien Chau district: 12 households).

bna_img_1551.jpg
Workers are operating a wire drawing machine at the VT 409 pole in Dien Thai commune, Dien Chau district. Photo: Thanh Duy

Of the 18 resettled households, 9 have houses on land, and the People's Committees of the districts are completing legal procedures to hand over the resettlement land. Currently, the households have basically dismantled their houses and handed over the land, while 1 household in Nghi Loc district is dismantling, expected to be completed before July 15, 2024, and 1 household in Hoang Mai town is expected to relocate before July 25, 2024, ensuring progress before connecting to the grid.

bna_img_1497.jpg
Provincial Party Secretary Thai Thanh Quy presents gifts to encourage cadres, workers, union members and youth at VT 409 column in Dien Thai commune, Dien Chau district. Photo: Thanh Duy

Leaders of Nghe An province have repeatedly directly inspected, urged and encouraged the forces at the site; at the same time, directed and supported the investor and contractor to organize the project construction locally in the spirit of "4 on-site" (construction machinery, unskilled labor, construction materials in the foundation stage and logistics).

bna_img_1338.jpg
The 500kV line 3 circuit section through Dien Thai commune is being pulled by the construction unit: Photo: Thanh Duy

This morning, Provincial Party Secretary Thai Thanh Quy directly inspected the construction at two positions of VT 409 column in Dien Thai commune, Dien Chau district and VT 422 in Do Thanh commune, Yen Thanh district.

Under the scorching hot weather, the investor, contractors, construction units, directly the engineers and workers on the construction site are focusing on construction with the spirit of "overcoming the sun, overcoming the rain, "eating quickly, sleeping urgently", working continuously 24/7, "3 shifts, 4 shifts", "not enough work during the day, working at night", "working through Tet, through holidays, through holidays", "only discussing work, not discussing back" as directed by the Prime Minister.

bna_img_1810.jpg
Provincial Party Secretary Thai Thanh Quy and the working delegation inspected the construction progress of the 500kV line circuit 3 in Do Thanh commune, Yen Thanh district. Photo: Thanh Duy
bna_img_1643.jpg
Provincial Party Secretary Thai Thanh Quy talks with leaders of the National Power Transmission Corporation at the construction site of pole VT 422 in Do Thanh commune, Yen Thanh district. Photo: Thanh Duy

Up to now, the province has completed casting foundations at 202/202 locations, erected 121 column locations, is erecting 81 column locations, completed pulling wires for 1 anchor span, and is pulling wires for 5 anchor spans.

Reporting to the Secretary of Nghe An Provincial Party Committee, the investor representative said that currently, the leaders are all staying at the construction site, directing forces and vehicles to focus on construction, striving to complete the project on schedule.

bna_img_1625.jpg
The Provincial Party Secretary and the working delegation surveyed the construction progress at the location of VT 422 pole in Do Thanh commune, Yen Thanh district. Photo: Thanh Duy
bna_img_1672.jpg
Workers are installing at the location of VT 422 column in Do Thanh commune, Yen Thanh district. The column is 74m high, with a material mass of 171 tons. Photo: Thanh Duy

At the inspection sites, comrade Thai Thanh Quy acknowledged the active and thorough participation of investors, contractors, and construction units; visited, encouraged, and commended officers, engineers, and workers who overcame the harsh heat to construct the project.

Through on-site inspection and understanding of the opinions of investors, units, and contractors, the remaining work (erecting columns, installing porcelain, pulling wires, and materials) requires professional, highly skilled, and experienced workers. The Secretary of the Nghe An Provincial Party Committee requested that units continue to make maximum efforts, overcome difficulties caused by the weather, and arrange enough human resources to both speed up construction progress and ensure quality and labor safety, contributing to bringing the entire project to the finish line on time.

bna_img_1690.jpg
Provincial Party Secretary Thai Thanh Quy visited and shared the hardships of workers at VT 422 pole in Do Thanh commune, Yen Thanh district when working in extremely hot weather conditions. Photo: Thanh Duy

Discussing with leaders of Dien Chau and Yen Thanh districts, Provincial Party Secretary Thai Thanh Quy noted the need to continue to ensure the best security and order; strictly manage the handed-over corridor; promptly support and resolve arising issues, creating the most favorable conditions for the project to ensure the set progress.

bna_img_1774.jpg
Provincial Party Secretary Thai Thanh Quy visited and encouraged construction workers at the VT 422 pole location in Do Thanh commune, Yen Thanh district. Photo: Thanh Duy

Talking to the youth union members, the head of the Provincial Party Committee acknowledged and commended the young people who have supported the project implementation in the past time (the whole province established 74 youth volunteer teams with the participation of more than 1,100 youth union members); thereby, requiring the need to continue to arrange forces to support construction units in traffic diversion, ensuring traffic during the wire pulling process, providing water for construction teams; sending forces to support cooking for workers if needed; supporting the return of the site after the completion of construction and continuing to propagate the importance of the 500kV line 3 to the people.

bna_img_1744.jpg
Provincial Party Secretary Thai Thanh Quy presents gifts to cadres, engineers and workers working at the VT 422 pole in Do Thanh commune, Yen Thanh district. Photo: Thanh Duy

On June 23, Prime Minister Pham Minh Chinh directly inspected the progress of the 500kV line 3 project through Thanh Hoa and Nghe An provinces and chaired a meeting with leaders of Nghe An and Ha Tinh provinces, Vietnam Electricity Group and the National Power Transmission Corporation at the headquarters of Nghe An Provincial People's Committee.

After the meeting, the Government Office issued Notice No. 288/TB-VPCP dated June 29, 2024 conveying the Prime Minister's conclusion.

Accordingly, for the three localities of Thanh Hoa, Nghe An, Ha Tinh, the head of the Government highly appreciated the initiative of the provincial leaders, the active participation of the entire local political system; commended the union members and youth who have promoted their youthfulness, dynamism, volunteerism, responsibility, creativity, and participated in building and developing the country in the spirit of "wherever there is a need, there is youth, where there is difficulty, there is youth".

The project is entering the final stage, the Prime Minister requested to urgently complete the remaining work with a spirit of high determination, greater efforts, and more drastic actions, because until completion and energization, there is still much work to do; in which, Vietnam Electricity Group and the National Power Transmission Corporation organize a special peak emulation period, "final", mobilizing all forces to participate in striving to complete the project in July 2024.

Featured Nghe An Newspaper

Latest

Nghe An Provincial Party Secretary Thai Thanh Quy inspects, encourages and urges the 500kV circuit 3 project
POWERED BYONECMS- A PRODUCT OFNEKO