Details of technical infrastructure items west of Binh Minh Street will be invested in and renovated by Cua Lo Town

Nhat Lan DNUM_CFZAIZCACC 08:11

(Baonghean.vn) - With the goal of building a modern - green - clean - beautiful coastal city, attracting tourists, facilitating the reorganization of business activities, the People's Committee of Cua Lo town has planned to renovate the overall urban technical infrastructure (parking lots, sidewalks, lighting, drainage ditches, trees...). This plan will be implemented from the fourth quarter of 2022 to 2025.

Cua Lo Town agrees on plan to clear constructions and kiosks on the east side of Binh Minh Street

23/08/2022

There are 11 technical infrastructure works that the People's Committee of Cua Lo town plans to invest in and renovate from the fourth quarter of 2022 to the first quarter of 2023, including: Renovation and upgrading of the town stadium; Lighting system for crossroad No. 10 (from Binh Minh street to Nguyen Hue street; Lighting system for Binh Minh street (phase 3) from Nguyen Xi street to Cua Lo port with a length of 1,100m; Sidewalks, lighting for crossroad No. 9 - Nguyen Duy Trinh with a length of 650m, sidewalk width of 8m (from Binh Minh street to Nguyen Hue street).

Sidewalk, lighting system of crossroad No. 9 - Nguyen Thuc Duong with length of 310m, sidewalk width of 5m (from Binh Minh street to Mai Thuc Loan street). Sidewalk system, lighting system of road 11A - Hoang Van Tam, with length of 620m, sidewalk width of 6m (from Binh Minh street to Nguyen Hue street). Sidewalk system, lighting system of road 11B - Dang Thai Thuyen, with length of 310m, sidewalk width of 6m (from Binh Minh street to Mai Thuc Loan street).

The sidewalk and drainage system of Mai Thuc Loan Street (from Sao Nam Street to Crossroad No. 5) is 570m long and 8m wide. The sidewalk and drainage system of Crossroad No. 13 (from Binh Minh Street to Nguyen Hue Street) is 610m long and 8m wide. The sidewalk of Ba Lua Street is 360m long and 12m wide and 3m wide. The sidewalk of Nguyen Su Hoi Street is 1,400m long and 4m wide.

Sidewalk systems, lighting systems... on many roads will be renovated and upgraded. Photo: Thanh Cuong

Also during this time, the People's Committee of Cua Lo town will use the budget to renovate, paint lines, and light the area outside the town's stadium (7,200 m2) make parking lots; paint lines and install signs on 7 routes (Crossroads 19 and 20 are 600m long; Road II' is 500m long; Road III (from Nguyen Xi Street to Crossroad No. 14 is 3,000m long; Road No. 5 and No. 6 (from Road II'-III) are 350m long; Road 14 is 600m long) to make a place to stop and park vehicles.

Mobilizing social resources (according to the plan for organizations and individuals to invest in collecting fees) to invest in building parking lots on BMC vacant land (5,245 m2); 5 vacant land locations between Highway 19 and Highway 21 (65,381 m2); vacant land west of the headquarters of the Town Construction Investment Project Management Board (1,050 m2).

From 2023, Cua Lo Town People's Committee will also use the old Van Minh Bus Station (880 m2);; Cua Lo II School yard (5,500 m2); Continuing Education Center campus (1,000 m2); West sidewalk of Nguyen Hue street, from Sao Nam street to 14 street (15,400 m)2); Cua Lo Bus Station (2,300 m)2) to make a parking lot.

From the first quarter of 2023 and the third quarter of 2023, the People's Committee of Cua Lo town will implement the green tree project on the roads, including: replacing the green tree system on Sao Nam street (from Binh Minh street to Nguyen Hue street), 650m long; planting new trees on Mai Thuc Loan street (from Sao Nam street to crossroad No. 5), 570m long; planting new trees on crossroad No. 13 (from Binh Minh street to Nguyen Hue street), 610m long.

In addition, focus on implementing the phase 2 wastewater treatment project (currently being deployed from crossroad No. 12 to crossroad No. 23), planned to be put into operation by the end of 2023; review to connect with the remaining cases that have level 1 and level 2 pipes to the treatment system; have a plan to connect the wastewater system of kiosks and restaurants (newly built) to the wastewater treatment system.

Opening some fishbone roads connecting Binh Minh Street to the inner cross-roads. Photo: Thanh Cuong

From 2023 to 2025, the People's Committee of Cua Lo town plans to invest in implementing 15 technical infrastructure projects, including: Lighting, sidewalks on Duong Thanh street (south of Hanoi Hotel), from Nguyen Su Hoi street to Long street III, length 520m; width 15m, sidewalk width 4m; Sidewalks, lighting on Dinh Hong Phien street (south of the old Van Minh bus station), length 530m, width 15m, sidewalk width 3.5m; Sidewalks, lighting on 12A - Tay Son street (from 12th street to 13th street), length 280m, width 9m; Roads, ditches, lighting, sidewalks on Trinh Cong Son street (fishbone road between 13th street and 14th street to Cua Lo gas station), length 300m, width 6.5m; Fishbone street lighting from Binh Minh Street to Street 2 (South of the Provincial Party Committee Hotel), 250m long, 10m wide; Fishbone street from Binh Minh Street to Nguyen Su Hoi Street (North of Thu Thuy Ward People's Committee headquarters), 120m long, 5.5m wide. Fishbone street from Binh Minh Street to Street 15m, 120m long, 5m wide.

Lighting on Luu Quang Vu Street (fishbone street south of Viet Anh Hotel, from Binh Minh Street to Road No. II), 300m long, 12m wide; Sidewalk, lighting on Tran Van Cung Street (from Binh Minh Street to Road No. II, north of Karaoke Max) 350m long, 11m wide, 2.5m wide sidewalk; Roadbed, road surface, sidewalk, lighting on Mai Thuc Loan Street (from crossroad No. 12 to crossroad No. 14), 760m long, 30m wide, 8m wide sidewalk; Sidewalk, lighting on Hoang Khanh Street; Sidewalk, lighting on Nguyen Cong Chinh Street, 230m long, 11.5m wide, 3m wide sidewalk; Sidewalk of crossroad No. 14 - Yet Kieu, 920m long, 30m wide, 8m wide sidewalk; Sidewalk of crossroad No. 12 - Hoai Thanh, length 630m, width 21m, sidewalk width 8m; Sidewalk, drainage ditch, Nguyen Sinh Cung street surface, length 3.8km, width 36m, sidewalk width 10.5m.

Cua Lo encourages organizations and individuals to do business in entertainment and recreation, using vacant land that has not been invested in construction south of Binh Minh Square. Photo: Thanh Cuong

Along with the overall technical infrastructure improvement plan, the People's Committee of Cua Lo townalso orient and arrange the culinary and entertainment business area. In which, the culinary business area is oriented to the North of Binh Minh Square (from Nguyen Sinh Cung street to crossroad number 5).

In these areas, households are encouraged to arrange food businesses on vacant land plots of organizations and individuals who have not yet invested in construction on the following streets: Mai Thuc Loan; Nguyen Thuc Duong; Nguyen Duy Trinh; Nguyen Thuc Tu; Le Thai Tong (2'); Nguyen Hue; Nguyen Duc Cong and vacant land plots south of the Square where people want to build food courts for business.

For entertainment business areas, organizations and individuals are encouraged to use vacant land that has not been invested in construction south of Binh Minh Square (from Road No. 12 - Hoai Thanh to Road No. 14 - Yet Kieu) to build entertainment, cultural, sports and tourism areas.