Enforced site clearance for the road connecting Lam River with National Highway 46

DNUM_CEZBBZCABH 11:54

(Baonghean.vn) - To complete the site clearance for the construction of the road connecting National Highway 46 with the Lam River road (also known as the 35m road), on the morning of November 24, Vinh City People's Committee forcibly recovered land from households in Xuan Hoa hamlet, Nghi Duc commune.

The enforcement session was witnessed by representatives of agencies and departments of Vinh city, Xuan Hoa hamlet, Nghi Duc commune; relevant units implementing the project and local residents.

» Vinh City sets date for compulsory land acquisition for road connecting Lam River with National Highway 46

Trước khi tiến hành cưỡng chế, các ban, ngành, đoàn thể đã thuyết phục gia đình ông Điều bà Chắt. Ảnh: Phương Thảo
Before carrying out the enforcement, the departments, branches and organizations persuaded the family of Mr. Nguyen Dieu - Mrs. Le Thi Chat (1 of 5 households that have not yet accepted the compensation and resettlement plan). Photo: Phuong Thao
Đọc quyết định cưỡng chế thu hồi đất đối với hộ gia đình ông Điều bà Chắt. Ảnh: Phương Thảo
Reading the decision to enforce land recovery for Mr. Dieu and Mrs. Chat's household. Photo: Phuong Thao
Tiến hành niêm phong, kiểm đếm tài sản. Ảnh: Phương Thảo
Conducting sealing and inventory of assets. Photo: Phuong Thao
Dỡ ngôi nhà nằm trong vùng đất quy hoạch thực hiện dự án. Ảnh: Phương Thảo
Demolition of a house located in the planned land area for project implementation. Photo: Phuong Thao

The project of connecting Highway 46 with Lam River Road is an important traffic route of Vinh city, approved by the Prime Minister with a planning limit of 35m. When completed, it will create a driving force to attract investment, urban embellishment, socio-economic development, and improve people's lives.

This project passes through Nghi An, Nghi Duc, Hung Loc, Hung Hoa communes (Vinh City) with a total of 130 households affected, requiring compensation and resettlement. As of November 24, the site clearance work has been basically completed; only 5 households have problems and have not yet accepted the general policy.

The reason for the households’ problems is related to the planning of the road connecting National Highway 46 with the Lam River road. According to the households, the Vinh City People’s Committee’s implementation of site clearance within a range of 35m, while there is no official decision from the competent authority, is not in accordance with the law.

In fact, according to the adjusted master plan of Vinh city approved by the Prime Minister in Decision No. 52/QD-TTg and Decision No. 4522/QD-UBND.CN dated November 25, 2011 of the Provincial People's Committee, the road connecting National Highway 46 with the Lam River road is planned to have a roadbed width of 35m.

In 2014, when the detailed design was made, the provincial and city budgets faced many difficulties. Therefore, the Vinh City People's Committee proposed to the Provincial People's Committee that, in the immediate future, it would invest in building a road connecting National Highway 46 with the Lam River road with a shoulder width of 12m and a clearance area of ​​15m. The proposal of the Vinh City People's Committee was approved by the Provincial People's Committee.

However, during the implementation process (in 2015 and 2016), the budget situation of the province and the city was guaranteed. In addition, most of the people in the area affected by the route requested to carry out site clearance according to the original planning of 35m, so the People's Committee of Vinh City proposed that the Provincial People's Committee allow compensation for site clearance through residential areas to be carried out according to the originally approved planning of 35m. This proposal of the People's Committee of Vinh City was approved by the Provincial People's Committee.

According to the approved plan, the road connecting National Highway 46 with the Lam River road must be completed by December 31, 2017. However, the handover of the land for the construction of the road has not been completed, not ensuring the construction progress. The City People's Committee and relevant agencies have organized dialogues and propaganda campaigns many times with households but have not yet achieved results.

Therefore, to complete the site clearance and hand over the site to contractors to construct the road on schedule, it is necessary to organize compulsory land acquisition.