Ensuring safety for construction of Vissai Cement Grinding Station and Port project
(Baonghean.vn) - On the morning of June 30, under the chairmanship of comrade Nguyen Xuan Duong - Deputy Secretary of the Provincial Party Committee and Chairman of the Provincial People's Committee, the Provincial People's Committee held a working session to resolve a number of existing problems to ensure security and safety for the construction of the Vissai Cement Grinding Station and Port project of The Vissai Cement Group in Nghi Thiet commune, Nghi Loc district.
Also attending were comrades: Nguyen Xuan Son - Standing Deputy Secretary of the Provincial Party Committee, Chairman of the Provincial People's Council; Colonel Nguyen Huu Cau - Member of the Provincial Party Committee, Director of the Provincial Police; Le Ngoc Hoa - Vice Chairman of the Provincial People's Committee, and representatives of relevant departments, Nghi Loc district, The Visssai Cement Group.
![]() |
Overview of the working session |
The Vissai Group is currently investing in a cluster of projects including: Song Lam Cement Joint Stock Company, Cement Grinding Station and International Port in Nghi Thiet Commune - Nghi Loc. This is a key cluster of projects in Nghe An and during the implementation process, the investor has always received attention from all levels and sectors, promptly resolving difficulties and problems.
![]() |
Comrade Nguyen Xuan Duong chaired the meeting. |
The compensation work for site clearance has been basically completed for the entire project to promptly hand over to the Investor for construction. Currently, the Investor is urgently implementing the construction of items of the Vissai Port Project such as leveling the ground in the inland port area, piling the wharf in the international port area. According to the Investor's project progress report, it is expected that phase 1 of the project will be completed by October 30, 2016.
![]() |
Colonel Nguyen Huu Cau - Member of the Provincial Party Committee, Director of the Provincial Police Department suggested that in order to do a good job of security and order during the project construction process, it is necessary to properly resolve the relationship between management agencies, local authorities and enterprises. |
However, some people do not agree with the policy of attracting investment to build projects in this area, the reason is that in Nghi Thiet commune, many large projects are being implemented at the same time: Cement grinding station, Port, DKC Petroleum Depot, D4 road... meanwhile, the propaganda and mobilization work is not very effective. The construction process of contractors has not implemented well the construction process and measures such as: Blasting unit, 110Kv power line construction unit, D4 construction unit...
![]() |
The representative of Nghi Loc District People's Committee requested that during the transportation of materials and equipment, the contractor must have measures to handle environmental pollution and minimize impacts on people. |
Therefore, during the construction of the Cement Grinding Station and Vissai Port, local people have repeatedly caused disorder and obstructed the construction. Road N5: Currently, 45 households in Nghi Thuan commune have not yet relocated and handed over the construction site, although the resettlement area has been completed. Of these, 5 households are stuck at Nhan Hoa Bridge, so construction cannot continue. Road D4: Currently, 36 houses are cracked due to the compaction of D4 construction.
![]() |
Representative of The Vissai Group speaking. |
After listening to the opinions of the departments, local authorities, and concluding the meeting, Chairman of the Provincial People's Committee Nguyen Xuan Duong requested: To ensure security and safety for investors to construct the project on schedule, Nghi Loc District People's Committee, relevant departments, and investors need to continue to propagate and mobilize people to ensure security and order, hand over the site to construct related works to ensure progress.
The provincial police have increased the number of personnel for the working group at the construction site of the Vissai Grinding Station and Port to monitor the situation and have a plan to promptly handle any incidents that may occur. They have directed the construction unit of Road D4 to regularly water the road to limit environmental impacts on the people.
![]() |
Construction of The Vissai seaport. |
Song Lam Cement Joint Stock Company needs to require contractors to strictly implement construction procedures and measures. The process of transporting raw materials and equipment must have measures to handle environmental pollution to minimize impacts on people. Speed up the construction progress of residential roads...
Conclusion of Chairman of Provincial People's Committee Nguyen Xuan Duong
.