Expected to put berths 5 and 6 of Cua Lo Port into operation in October 2017

DNUM_ACZAGZCABH 11:02

(Baonghean.vn) - With the investment of Tuan Loc Construction Joint Stock Company, berths 5 and 6 of Cua Lo Port are speeding up construction progress, expected to be completed ahead of schedule. After inspection, Vice Chairman of the Provincial People's Committee Huynh Thanh Dien requested relevant parties to promptly complete administrative procedures, to put into operation in October 2017.

Bến cảng 5,6 của Cảng Cửa Lò do Công ty CP xây dựng Tuấn Lộc đầu tư đang đẩy nhanh tiến độ thi công. Ảnh: Nguyên Sơn
Wharf 5.6 of Cua Lo Port invested by Tuan Loc Construction Joint Stock Company is speeding up construction progress. Photo: Nguyen Son

On the morning of June 2, Mr. Huynh Thanh Dien - Vice Chairman of the Provincial People's Committee and a working delegation including leaders of the Department of Transport, Planning and Investment, Construction, Natural Resources and Environment, Dong Nam Economic Zone and the Provincial People's Committee Office inspected the construction progress of Wharf No. 5 and 6 at Cua Lo Port invested by Tuan Loc Construction Joint Stock Company. Also working were representatives of the leaders of Cua Lo Town and Nghe An Port Authority.

The project is designed to accommodate ships with a capacity of 30,000DWT. It is a container port, so it requires very high investment and construction techniques.

The investor plans to complete the project in August 2017, ahead of schedule (originally scheduled for November 2017). Currently, the bored pile part with 647 piles has been completed on a total area of ​​22,500m2. Each pile is driven 35m - 38m deep. The container yard part has 100% completed foundation, and is being paved with high-strength concrete blocks.

Nhân lực và phương tiện được tăng cường cho công tác thi công. Ảnh: Nguyên Sơn
Human resources and equipment are increased for construction work. Photo: Nguyen Son

The investor spent over 400 billion VND on the items of the wharf and wharf No. 5. Along with wharfs No. 5 and 6, there is also the Cua Lo Port logistics area, with a total area of ​​23.4 hectares. The wharf is 450m long and 40m wide, capable of receiving 2 ships with a capacity of 30,000 tons at the same time. The total investment of the project is 1,180 billion VND.

Working with the provincial delegation, Cua Lo Port Company Limited and investor Tuan Loc Construction Joint Stock Company proposed that Nghe An province and units and localities develop a plan to open a road to the port area 5,6. Because the port construction progress is accelerating, it may exceed the schedule, but the access road is currently shared with berths 1,2,3,4. If there are many goods and vehicles entering to load and unload, it will be overloaded, causing congestion.

Đồng chí Huỳnh Thanh Điền cùng đoàn công tác kiểm tra thực địa thi công bến cảng 5,6 Cảng Cửa Lò. Ảnh: Nguyên Sơn
Comrade Huynh Thanh Dien and the working group inspected the construction site of wharf 5,6 of Cua Lo Port. Photo: Nguyen Son
Các vật liệu được tập kết cho thi công bến cảng 5,6 Cảng Cửa Lò. Ảnh: Nguyên Sơn
Materials are gathered for the construction of wharfs 5 and 6 of Cua Lo Port. Photo: Nguyen Son

The units also requested the province and Cua Lo town to quickly and resolutely relocate the fishing wharf, creating favorable conditions for large tonnage ships to enter and exit.

Comrade Huynh Thanh Dien requested Nghe An Port Authority to actively assist investors in completing procedures for opening and announcing port operations; assigning the People's Committee of Cua Lo town to actively urge the resettlement project and relocation of the fishing wharf, ensuring the operation of the Cua Lo Port area in general. The deadline for relocating the fishing wharf is the end of 2017.

Toàn cảnh buổi làm việc giữa Phó chủ tịch UBND tỉnh với các sở, ngành, địa phương và nhà đầu tư Công ty CP Tuấn Lộc. Ảnh: Nguyên Sơn
Overview of the working session between the Vice Chairman of the Provincial People's Committee with departments, branches, localities and investors of Tuan Loc Joint Stock Company. Photo: Nguyen Son

Regarding the access road to the port, in the immediate future, Cua Lo town needs to study the route serving the port exploitation before the province invests in the road to berths 5 and 6. The Vice Chairman of the Provincial People's Committee requested relevant agencies to strengthen coordination and accompany investors to ensure the waterway and legal procedures for the new port to come into operation.

» Tuan Loc Group's port in Nghe An is preparing to be put into operation.

Nguyen Son

RELATED NEWS

Featured Nghe An Newspaper

Latest

x
Expected to put berths 5 and 6 of Cua Lo Port into operation in October 2017
POWERED BYONECMS- A PRODUCT OFNEKO