Overcoming material difficulties to construct the North-South expressway, Dien Chau - Bai Vot section

PV Group DNUM_AHZAGZCACC 10:07

(Baonghean.vn) - Taking advantage of favorable weather, construction units are focusing maximum human resources, machinery, and equipment to speed up the construction progress of the North-South expressway, Dien Chau - Bai Vot section.

The North-South Expressway construction component project, Dien Chau - Bai Vot section, is invested by the joint venture of Hoa Hiep Company Limited - CIENCO4 Group Joint Stock Company - Nui Hong Investment Company Limited - Truong Son Construction Corporation - VINA2 Investment and Construction Joint Stock Company. Currently, the contractors are concentrating all their machinery to carry out the construction. Photo: PV
The project has a total length of 49.30km, passing through the districts of Dien Chau (11.44km); Nghi Loc (7.14km); Hung Nguyen (25.88km) and Duc Tho (4.84km). Of which, there are 40km of agricultural land (accounting for 81.2%); 4.65km of residential land (accounting for 9.4%) and 4.65km of forest land (accounting for 9.4%). In the photo, the construction unit is constructing Than Vu tunnel with a length of about 1.1km connecting Dien Phu commune (Dien Chau) and Nghi Dong (Nghi Loc). Photo: PV

Up to now, the Project Management Board 6 and the local land acquisition councils have cleared 49.22km of land (reaching 99.84%), currently only the power line system on the route and 80m through a resettlement residential area in Hamlet 5, Nghi Dong Commune, Nghi Loc District are still stuck. In the photo, contractors are rushing to construct the section through Dien Phu Commune (Dien Chau). Photo: Tien Dong

Mr. Nguyen Quoc Viet - General Director of Phuc Thanh Hung Investment Joint Stock Company (Project Enterprise), said: Taking advantage of favorable weather, contractors are mobilizing maximum human resources, machinery and equipment to carry out construction. Currently, the mines of earth filling materials basically meet the demand, however, due to uneven distribution, transportation costs are high, some mines have prices much higher than estimated, making it very difficult for contractors. For sand mines, the reserves meet the demand, but due to the low exploitation capacity of the mines, contractors have to use many mines to meet the schedule. Photo: Tien Dong

On this occasion, the weather was favorable, so the contractors mobilized 100% of their human resources and machinery, divided into many shifts for construction. The contractors even took advantage of the night, when the weather was cool, to pour concrete. In the photo, the contractor constructed the Hung Duc bridge (4km long), spanning the Lam River, connecting Hung Nguyen (Nghe An) and Duc Tho (Ha Tinh), at night. Photo: Tran Chau

However, according to Mr. Viet, recently the input prices of construction materials have increased dramatically, from iron, steel, cement, sand, stone, asphalt, etc., leading to an increase in the price of bid packages of about 13% - 15%. In addition, the price of land at the mines has also increased about 2 times compared to the unit price in the bid package estimate, which has greatly affected investors. Photo: Tien Dong

Currently, to ensure payment volume, meet the conditions for disbursement of loans and State capital contributions in June 2022, in the coming time, contractors have determined to mobilize more construction teams, increase equipment at existing construction teams, organize overtime and especially immediately add construction teams to handle weak ground and large bridge construction teams at locations such as Than Vu tunnel, Xuan Duong bridge, Hung Duc bridge, QL8A intersection... to contribute to bringing the project to the finish line on schedule. It is known that so far, investors have contributed 647 billion VND for construction (4 investors). According to the 2022 plan, investors must contribute 824 billion VND to ensure counterpart capital and construction. Photo: PV
Currently, contractors are also speeding up the construction progress of the North-South Expressway project, Nghi Son - Dien Chau section. In the photo, the Truong Vinh tunnel connecting Nghe An and Thanh Hoa provinces has also been opened, construction units are starting to reinforce the tunnel shell, lower the foundation... Photo: Tran Chau