Vice Chairman of Nghe An Provincial People's Committee Hoang Phu Hien inspects the progress of the coastal road

Tien Dong DNUM_AJZAEZCACF 12:40

On the morning of April 9, comrade Hoang Phu Hien - Member of the Provincial Party Executive Committee, Vice Chairman of the Provincial People's Committee, along with representatives of a number of departments and branches inspected the construction progress of the coastal road.

Vice Chairman of the Provincial People's Committee Hoang Phu Hien, inspecting the progress of site clearance and construction of the coastal road. Video: Tien Dong

The coastal road project from Nghi Son (Thanh Hoa) - Cua Lo (Nghe An) from Km7-Km76 has the scale of a grade III plain road, with a road surface width of 11m.

bna_nl.jpg
The project inspection team at the section passing through Nghi Quang commune, Nghi Loc district. Photo: Tien Dong

The entire project has 8 bridges, including 5 large bridges and 3 small bridges. The total investment of the project is 4,651 billion VND, of which the construction cost is 3,202 billion VND; the site clearance cost is 933.6 billion VND; the contingency cost and other costs are 515.4 billion VND.

bna_nl2.jpg
The section passing through Nghi Quang commune (Nghi Loc) is currently facing land acquisition issues, making construction difficult. Photo: Tien Dong

The project is divided into 2 packages, in which package XL01 is implemented from Km7+00 to Km48+250; package XL02 is implemented from Km48+250 to Km76+00.

bna_dc.jpg
The delegation listened to Dien Chau district's opinion on the land acquisition problem in the section passing through Dien Thanh town. Photo: Tien Dong

In the past time, contractors have focused on human resources and equipment to implement construction, and have so far completed 89.2% of the contract.

bna(1).jpg
A family's house in Dien Thanh town (Dien Chau) has not yet been relocated. Photo: Tien Dong

Currently, the land acquisition and clearance work still has 0.37km to be completed, of which Hoang Mai Town has 1 household with 0.04km not completed; Quynh Luu has 9 households with 0.16km; Dien Chau has 1 household with 0.02km; Nghi Loc has 7 households with 0.15km. This causes some items to be behind schedule.

bna_ql.jpg
Checking the section through Quynh Luu district. Photo: Tien Dong

During the on-site inspection, Mr. Hoang Phu Hien - Vice Chairman of the Provincial People's Committee requested that localities speed up the site clearance progress to hand over to the contractor.

bna_hm.jpg
Inspection team working in Hoang Mai town. Photo: Tien Dong

At the same time, the Traffic Project Management Board - Department of Construction is required to direct contractors to speed up progress, review construction sites, especially intersections with inter-district and inter-commune roads, and promptly complete the system of markers, signs, etc. to ensure traffic safety.