Vice Chairman of Nghe An Provincial People's Committee inspects the progress of Hoang Mai Industrial Park Project

Thanh Le DNUM_BGZAJZCACE 16:04

Vice Chairman of Nghe An Provincial People's Committee Bui Thanh An requested departments, branches, localities and investors to focus on implementing tasks more drastically, removing difficulties and obstacles in site clearance for Hoang Mai II Industrial Park project.

On September 16, Comrade Bui Thanh An - Member of the Provincial Party Standing Committee, Vice Chairman of the Provincial People's Committee directly inspected and worked on the implementation of the Hoang Mai I and Hoang Mai II Industrial Park projects. Accompanying him were representatives of provincial departments, branches and sectors and Hoang Mai town.

 làm việc
Working delegation with Hoang Mai town and investors: Photo: TL

Remove obstacles

ProjectHoang Mai II Industrial ParkThe Prime Minister approved the investment policy and approved the investor Hoang Thinh Dat Joint Stock Company in October 2023. The project area is 334.79 hectares, with a total registered investment capital of VND 1,900 billion.

Currently, the Department of Natural Resources and Environment has approved the first and second phase of measurement of 183.1 ha/334.79 ha. For the remaining area of ​​about 151.69 ha, there are still some problems with overlapping boundaries, incorrect locations, areas, etc., so it is not qualified to submit to the Department of Natural Resources and Environment for approval.

 nhà đầu tư
Investor representative reports on project progress. Photo: TL

At the meeting, investor representatives recommended that the locality should speed up site clearance, complete infrastructure and hand over land for signed projects.

According to the leaders of Hoang Mai town, the work of compensation and site clearance is facing many difficulties and obstacles. During the measurement process, there are overlapping boundaries, incorrect locations and areas. The origin of the land is unclear, has many owners, lacks legal documents, there are disputes, overlaps, and the subject of land allocation has not been determined. On the other hand, determining assets such as trees and crops on the land is difficult because there are no specific regulations and instructions for cases of intercropping many types of trees at high density.

 a trị
Comrade Le Tien Tri - Member of the Provincial Party Committee, Head of the Southeast Economic Zone Management Board spoke at the meeting. Photo: TL

At the meeting, leaders of departments, branches, Hoang Mai town and Hoang Thinh Dat Joint Stock Company focused on exchanging, analyzing and discussing solutions to solve problems and difficulties in compensation and site clearance.

Implement vigorously

Concluding the meeting, the Vice Chairman of the Provincial People's Committee emphasized: Hoang Mai II Industrial Park Project is a key project of the province. In recent times, the provincial leaders have paid great attention to directing, Hoang Mai town and functional sectors to make efforts to carry out the site clearance work of Hoang Mai II Industrial Park.

He acknowledged the efforts and responsibilities of departments, branches, localities and investors in implementing the project; and shared the difficulties with Hoang Mai town in the process of implementing the project.

 a hào
Comrade Pham Van Hao - Vice Chairman of Hoang Mai Town People's Committee reported on difficulties and obstacles in site clearance work. Photo: TL

To ensure the progress of handing over the site to investors and implementing essential infrastructure items within and outside the scope of the projects, the Vice Chairman of the Provincial People's Committee requested departments, branches, localities and investors to focus and implement the tasks more drastically from the viewpoint of the Working Group and the branches continuing to closely coordinate with Hoang Mai town when there are problems.

Specifically, for Hoang Mai town, it is necessary to focus on completing procedural documents, along with propaganda and mobilization work to get people to agree on a compensation and site clearance plan to hand over the site to investors to implement the project to ensure progress.

"The Standing Committee of Hoang Mai City Party Committee needs to regularly work with investors, listen to the situation to focus on directing the removal of obstacles. The compensation council must have a specific progress plan. The goal is to complete 11.6 hectares of the Thien Nang project before October 15; in 2024, complete 58 hectares of the Hainan Drinda project and essential infrastructure of Hoang Mai Industrial Park" - the Vice Chairman of the Provincial People's Committee emphasized.

 kết luận
Comrade Bui Thanh An - Vice Chairman of the Provincial People's Committee spoke at the meeting. Photo: TL

ForSoutheast Economic Zone Management Board, Vice Chairman of the Provincial People's Committee Bui Thanh An requested the committee to closely follow its tasks, take the lead and coordinate with relevant departments to propose carefully reviewing the land return by the people before approving the site clearance. In addition, the economic zone needs to coordinate with the Department of Natural Resources and Environment to quickly complete the procedures to terminate the operation and reclaim the land of the Nghi Son Foods project to Hoang Thinh Dat Joint Stock Company before October 15.

 an
Visiting the silicon bar and semiconductor wafer manufacturing plant of Runergy New Energy Science and Technology Group in Hoang Mai I Industrial Park. Photo: TL

For the Department of Natural Resources and Environment: Coordinate with the Southeast Economic Zone Management Board to reclaim and hand over land of the Nghi Son foods project to investors before September 30; provide opinions, guidance, and review cancellation documents for the People's Committee of Hoang Mai town; advise on land allocation according to the site clearance regime; advise the Provincial People's Committee to decide to replace Decision No. 24/2022/QD-UBND dated February 14, 2022 in accordance with the law, most convenient for site clearance compensation work in the whole province.

 nhà máy
The delegation visited the production line of Runergy Group in Hoang Mai I Industrial Park. Photo: TL

Department of Finance, continue to coordinate with Department of Agriculture and Rural Development to apply compensation for dense intercropping; advise on approval of contract estimates for real estate consulting units.

The Department of Agriculture and Rural Development continues to support land valuation and the Department of Finance to guide compensation for intercropping. The Land Registration Office coordinates to support Hoang Mai town in measuring, disseminating, and mobilizing people to agree on the policy.

 kiểm tra
The delegation listened to an introduction about Runergy Group's factory in Hoang Mai I Industrial Park. Photo: TL

Regarding the drainage system around Hoang Mai II Industrial Park, the Vice Chairman of the Provincial People's Committee assigned the People's Committee of Hoang Mai town to urgently give opinions on the investment proposal dossier as requested by the Southeast Economic Zone Management Board, to be completed before September 20, 2024; update and supplement the project to the Hoang Mai town land use planning in accordance with regulations, send it to the Department of Planning and Investment for appraisal and approval in accordance with regulations.

Regarding the drainage system from the downstream of Doi Tuong Lake to Hoang Mai River, Hoang Mai Town People's Committee continues to implement the direction of the Provincial People's Committee in Notice No. 472/TB-UBND dated June 21, 2024, urgently survey, research, and report solutions to handle the above drainage system before September 30, 2024.

 sản xuất
Production activities at Hoang Mai Industrial Park I. Photo: TL

Previously, Vice Chairman of the Provincial People's Committee Bui Thanh An and leaders of departments, branches and Hoang Mai town inspected the actual site clearance work of the Project "Investment in construction and business of infrastructure of Hoang Mai II Industrial Park" in Quynh Vinh commune; Visited the silicon bar and semiconductor disc manufacturing factory of Runergy New Energy Science and Technology Group in Hoang Mai I Industrial Park.

The Runergy New Energy Science and Technology Group (Runergy) Silicon Bar and Semiconductor Wafer Factory Project was granted an investment certificate in early 2023 with a total investment capital of up to 293 million USD (about 6,900 billion VND). Accordingly, the project covers an area of ​​30 hectares, built in Hoang Mai I Industrial Park in the Southeast Nghe An Economic Zone. The factory is expected to have a production capacity of 14,635 tons of silicon bars/year and 995 million 182-millimeter semiconductor wafers/year. These are two important components in the production of solar cell modules/.