Tan Ky speeds up construction progress of Huong - Phu - Hanh route before flood season

Xuan Hoang DNUM_CAZAIZCACD 14:50

(Baonghean.vn) - After more than 8 months of construction, the Huong - Phu - Hanh route (provincial road 534D), the works on the route have been basically completed before the flood season, striving to have the innermost 5 km paved by the end of 2023.

bna_duong 6.JPG
The Do Luong spillway bridge, on Route 534D, is being accelerated. There are 7 bridges on this route, all of which have completed the piers and piers. Photo: Xuan Hoang

Present at the project to expand and upgrade the routeProvincial Road 534D(the route connecting Tan An intersection to the inner communes: Huong Son, Phu Son and Nghia Hanh) on a day in mid-August showed that the contractor mobilized maximum means, machinery and human resources to deploy in the most urgent manner.

Observations show that the entire route has been widened, some slopes have been lowered, many sections of the road have been filled with crushed stone, flattened... the reinforced concrete bridges and culverts are gradually being completed.

bna_duong 1.JPG
The contractor is creating a road surface for people to travel conveniently during the project implementation. Photo: Xuan Hoang

The people of Huong Son commune hope that not only will the road be upgraded, but the national power grid will also be replaced, so that people can feel more secure when the rainy season comes and the quality of electricity will be improved. The people's biggest wish is that the road will be completed soon so that people can travel conveniently, have conditions to develop the economy, and their children can go to school with less difficulty.

District Project Management BoardTan Kysaid that with the consensus and voluntary donation of land by people living on both sides of the road, the site clearance work was smooth right from the start of the project. After more than 8 months of construction, the project has disbursed 45 billion VND, and is expected to disburse 50 billion VND by the end of 2023.

bna_duong 2.JPG
There are 16 culverts on the route, which have been basically completed. Photo: Xuan Hoang

To date, the contractor has laid out 18/18 km of the route; at the same time, the works on the route are also being urgently deployed. It is expected that by the beginning of the next rainy season, 7/7 reinforced concrete bridges and 16 culverts across the road will be basically completed, and the replacement of the national power grid will also be completed before the rainy season. Strive to have 5 km of the innermost road paved by the end of 2023.

The project to expand and upgrade Road 534D was approved by the State with a total investment of more than 148 billion VND, implemented in 3 years, expected to be completed by the end of 2024.

bna_duong 3.JPG
The construction unit continues to lower the slope according to the design at some sections on the route. Photo: Xuan Hoang

Mr. Phan Van Giap - Chairman of Tan Ky District People's Committee said: Route 534D (Huong - Phu - Hanh road) is the most difficult main road in the district, because after many years of not being invested in upgrading, the road is narrow... vehicles participating in traffic face many difficulties, especially vehicles transporting raw materials in and out of the area. Therefore, when the State invests in upgrading and expanding this route, the district focuses on directing relevant departments and offices to coordinate with contractors to speed up the construction progress, in order to disburse capital on schedule. In particular, before the flood season, the construction unit is speeding up the progress of works on the route, such as bridges, culverts... to limit the damage caused by floods.

"After completing this route, Tan Ky district will basically solve the traffic difficulties, creating conditions for people in the communes of Huong Son, Phu Son, Nghia Hanh and Tan An to exploit the potential and develop the agricultural and forestry economy," said Mr. Phan Van Giap.