What do you see in Dong Hoi after nearly 15 years of industrial park planning?

Tien Dong October 2, 2024 13:35

After nearly 15 years of planning, Dong Hoi Industrial Park in Hoang Mai Town still cannot take shape.

Bản đồ khu vực ĐH
Dong Hoi Industrial Park was first approved for detailed construction planning in Decision No. 02/QD-UBND.CN dated January 4, 2010, by the People's Committee of Nghe An province. This industrial park is located in Quynh Lap and Quynh Loc communes of Hoang Mai town. Initially, the planned area of ​​this industrial park was 1,436 hectares; total investment capital was 5,388 billion VND, with an operating period of 50 years. In the photo, a map of Dong Hoi area. Photo: Tien Dong
Bảng chỉ dẫn
According to the initial planning, Dong Hoi Industrial Park is a multi-industry industrial park such as thermal power industry; thermal power support industry; cement industry; shipbuilding industry; rope, cable, cordage and fishing gear manufacturing industry; seasoning powder processing industry; mechanical repair industry. This industrial park is also determined to be associated with the Dong Hoi seaport system, which has been approved by the Ministry of Transport for detailed planning in Decision No. 838/QD-BGTVT dated April 28, 2011. However, after many years, this area only has a few factories in operation, while other investment project portfolios have not yet taken shape. In particular, Dong Hoi port has not been built yet. In the photo, the sign to Dong Hoi Port. Photo: Tien Dong
 Đường ra cảng
Currently, this area has only built a 600m long road to Dong Hoi Port. Meanwhile, many projects with great expectations such as Kobe Sponge Iron Factory Project - Kobelco Sponge Iron Vietnam Co., Ltd., have been terminated. Photo: Tien Dong
bna_duong.jpg
From above, the road to Dong Hoi Port can be easily seen, while the surrounding landscape is still wild, with only a few production facilities in operation. Photo: Tien Dong
bna_duong(1).jpg
The fact that only a few projects have come into operation has caused this area to not develop as expected. Photo: Tien Dong
bna_666.jpg
Many large shrimp ponds of some businesses and units are located on both sides of the road to Dong Hoi Port. Photo: Tien Dong
Eo biển
It is known that on February 15, 2023, on behalf of the Prime Minister, Deputy Prime Minister Tran Hong Ha signed Decision No. 93/QD-TTg approving the overall adjustment of the Master Plan for the construction of the Southeast Nghe An Economic Zone, Nghe An province until 2040. In which, Dong Hoi Industrial Park is located in Area 2 of the Southeast Economic Zone, with an area of ​​600 hectares. This will be an area for the development of multi-industry industries, electricity industry, mechanical industry, cement industry, shipbuilding industry, aquatic product processing industry, seafood, forestry products, etc. associated with Dong Hoi general seaport. Hopefully, after being adjusted, Dong Hoi Industrial Park will soon develop, becoming an important growth pole for the province's economy. Photo: Tien Dong