Vinh City: Speed up compensation progress for key projects
(Baonghean.vn) - On June 7, Vinh City Party Committee held a meeting of the Steering Committee for compensation, support, and site clearance for key projects in the city.
Comrade Vo Viet Thanh - Member of the Provincial Party Standing Committee, Secretary of Vinh City Party Committee chaired the meeting.
In the past time, the Steering Committee for compensation, support and site clearance for key projects together with the departments and offices of Vinh City have made great efforts in site clearance. Up to now, the city has basically handed over almost all of the site area to the construction units at the works under the Vinh urban development project.
![]() |
Overview of the meeting |
However, some projects still have difficulties and problems such as: Quan Bau resettlement area project, 98% of land has been cleared, the project to build a regulating lake has been cleared 80%, the remaining area is agricultural land in Hung Loc, Hung Hoa communes and Hung Dung ward, the origin of land use has not been confirmed. The project to upgrade and renovate the moat around Vinh ancient citadel has been cleared 80%, the remaining land area in Cua Nam, Quang Trung, Doi Cung wards is still stuck because households have not agreed to the resettlement plan.
The Hung Tay – Vinh road construction project (72m road) has a total planned area of 23ha in Hung Dong commune and Quan Bau ward. The agricultural land has been cleared and the compensation for cemetery land, traffic land and irrigation land has been basically completed. The remaining residential land and land of organizations and units are in the process of confirming the origin of land use, expected to be completed before June 10, 2016....
![]() |
Construction of Vinh Ancient Citadel project (Photo: Tran Chau) |
For key investment projects of the province such as: Investment project to build new area B of Nghe An General Hospital, 24m planning project connecting Ho Tong Thoc street to Hoang Phan Thai street, renovation project of area A of Quang Trung apartment building, and Vinh University project are still stuck because some households have not agreed to the compensation price for land acquisition.
Speaking at the meeting, Comrade Vo Viet Thanh - Secretary of the City Party Committee acknowledged the achievements of departments, offices, units and localities in site clearance work in the past time. To complete the set goals, he requested relevant units to have stronger and more drastic solutions, focusing on propaganda and mobilizing affected households to comply with policies on site clearance work. At the same time, he requested investors and construction units to speed up the progress of projects, ensure security, order and environmental sanitation at construction sites.