Operation and regulation of water reservoir of Chi Khe Hydropower Plant (Con Cuong)

Viet Phuong DNUM_CGZAJZCACD 18:18

(Baonghean.vn) - The Standing Office of the Provincial Steering Committee for Natural Disaster Prevention, Search and Rescue and Civil Defense has just received Notice No. 09/2023/TB-CT dated September 26, 2023 from Chi Khe Hydropower Plant on the operation and regulation of water in the Chi Khe Hydropower Plant reservoir.

To ensure the safe regulation of water in Chi Khe Hydropower Plant's reservoir according to the approved single-reservoir process and inter-reservoir process on the Ca River basin, Chi Khe Hydropower Plant plans to operate and regulate water in Chi Khe Hydropower Plant's reservoir as follows:

Estimated time of spillway discharge: At 20:00, September 26, 2023.

Total discharge volume is about 500 m3/s to 850 m3/s (including through the spillway and generation through the generators) and may vary depending on the water flow to the lake.

Time to end water discharge through spillway: Until water flow into the lake is equivalent to power generation flow through generators.

1.jpg
Chi Khe Hydroelectric Plant. Photo courtesy

The Standing Office of the Provincial Steering Committee for Natural Disaster Prevention, Search and Rescue and Civil Defense informs the People's Committees of the districts: Con Cuong, Anh Son, Do Luong, Thanh Chuong, Nam Dan, Hung Nguyen and Vinh city; Heads of provincial departments, branches and sectors; Road Management Area II to inform the authorities at all levels, agencies, units, investors who are constructing along the river, on the river, owners of water transport vehicles and all people in the area downstream of Chi Khe Hydropower Plant to know and deploy necessary work, ensuring the safety of life and property of the State and people.