Operation and regulation of water reservoir of Chi Khe Hydropower Plant (Con Cuong)
(Baonghean.vn) - The Standing Office of the Provincial Steering Committee for Natural Disaster Prevention, Search and Rescue and Civil Defense has just received Notice No. 09/2023/TB-CT dated September 26, 2023 from Chi Khe Hydropower Plant on the operation and regulation of water in the reservoir of Chi Khe Hydropower Plant.
To ensure the safe regulation of water in Chi Khe Hydropower Plant's reservoir according to the approved single-reservoir process and inter-reservoir process on the Ca River basin, Chi Khe Hydropower Plant plans to operate and regulate water in Chi Khe Hydropower Plant's reservoir as follows:
Estimated time of spillway discharge: At 20:00, September 26, 2023.
Total discharge is about 500 m3/s to 850 m3/s (including through spillways and power generation through generators) and may vary depending on the water flow to the lake.
Time to end water discharge through spillway: Until the water flow to the lake is equal to the power generation flow through the generators.

The Standing Office of the Provincial Steering Committee for Natural Disaster Prevention, Search and Rescue and Civil Defense informs the People's Committees of the districts: Con Cuong, Anh Son, Do Luong, Thanh Chuong, Nam Dan, Hung Nguyen and Vinh city; Heads of provincial departments, branches and sectors; Road Management Area II to inform the authorities at all levels, agencies, units, investors who are constructing along the river, on the river, owners of water transport vehicles and all people in the area downstream of Chi Khe Hydropower Plant to know and deploy necessary work, ensuring the safety of life and property of the State and people.