Vietnam Road Administration issued an Order to build an emergency project to overcome subsidence at Chuoi slope, Que Phong district (Nghe An).
The purpose is to ensure smooth traffic and safety for vehicles and traffic participants on the section through Chuoi slope on National Highway 16 while waiting for a complete repair.

Deputy Director of the Vietnam Road Administration Nguyen Manh Thang has just signed Decision No. 2976/QD-CDBVN promulgating the Order to build emergency works to overcome the consequences of natural disasters on the route from Km264+300÷Km264+900 of National Highway 16, Nghe An province caused by heavy rains from July 12, 2024 to July 15, 2024 (Chuoi slope area, Chau Kim commune, Que Phong district).
The total estimated investment for the repair is 4.9 billion VND from the State budget (funding source for road economic activities) invested by Nghe An Department of Transport, expected to be implemented and completed before October 30, 2024.
Accordingly, the construction unit will clear mud, soil, and collapsed rocks from the positive slope that are still overflowing and filling the foundation, road surface, and longitudinal ditches; transport mud, soil, and rocks to the gathering location agreed upon by the local authorities according to regulations. The volume of mainly excavated soil is about 1,350m3.
At the same time, excavate and unload the unstable soil and rock on the positive slope, transport the soil and rock to the assembly location according to regulations; after excavating and unloading, construct a steel cage revetment at the foot of the positive slope at Km264+300 to increase slope stability, limit mud, soil, and rock from sliding onto the road surface, ensure underground drainage, and improve traffic safety. The main volume is about: excavating and lowering the slope of 18,824m3; arrange 240 stone cages of size (2x1x1)m.
Make a temporary road close to the left side of Km264+700 with a flexible curve radius but ensuring the largest allowable according to terrain conditions; base width 6m, road surface wider than 4m with pavement structure with a base of 144 stone gabions of size (2x1x0.5)m, covering 560m2Cover the surface and sides of the gabion with geotextile fabric; the upper foundation is made of crushed stone or water crushed stone to ensure that the asphalt pavement structure has a lifespan suitable for the time of ensuring traffic until the repair of the section is completed; reinforce the horizontal drainage culvert to ensure drainage of the terrain. The main volume is to make the temporary pavement with crushed stone or water crushed stone, asphalt with an area of 280m2.
Fully supplement the system of signs, install soft guardrails, markers, warning lights... at necessary locations on the route.
Vietnam Road Administration noted: During the implementation process, this is an area with very complex geology, groundwater, and a risk of continued landslides. Therefore, the investor needs to direct consultants to conduct geological and hydrological surveys and inspections to select a suitable groundwater treatment plan and excavation and offloading scope.
Before the Emergency Construction Order was issued, from July 12-15, 2024, at this location, the road was filled with gravel aggregate to connect the two ends of the road and the area of the collapsed road surface to ensure temporary traffic; poured M100 cement mortar to fill the cracks on the asphalt road surface, reinforced the curb and longitudinal ditch. The main volume is about: filling with soil, gravel aggregate 175m3; pour cement mortar into the 1.5m crack3.
From July 16 to 20, 2024, during the monitoring of the landslide location on the roadbed, it was found that the subsidence continued to develop, making it unsafe to travel, so the Nghe An Department of Transport directed the excavation of soil and rock to expand towards the positive slope, leveling, combining with filling in ditches, building temporary roads with soil, graded with type II crushed stone to serve traffic. Dismantle the traffic safety system (corrugated iron guardrails, signs, ...) within the subsidence and damage area; ensure traffic for rudimentary vehicles and motorbikes for groups of 5 to 7 people to pass through in non-rainy weather conditions and during the day. The main volume is about: digging the roadbed 520m3; 30m rock breaking3; 540m roadbed restoration3.
At the same time, install signs, barriers, warning lights... at both ends of the collapsed road and coordinate with local authorities in organizing guard duty to ensure traffic according to regulations.
Previously, on July 30, 2024, Deputy Minister of Transport Nguyen Duy Lam signed and issued Decision No. 952/QD-BGTVT announcing a natural disaster emergency to respond to and repair damage to road traffic infrastructure at the route from Km264+300 - Km264+900 of National Highway 16 caused by heavy rains in Nghe An province from July 12 to 15, 2024.
In particular, the Vietnam Road Administration and Nghe An Department of Transport are assigned to manage and implement disaster recovery activities according to the prescribed scope and responsibility, including reviewing and determining the specific extent of damage to road works caused by natural disasters, solutions for repair and remediation, and issuing an Order to build emergency works to overcome the consequences of natural disasters according to the provisions of law.
Previously, from July 12-15, 2024, heavy rain frequently occurred in some places in Que Phong district; on the evening of July 14, heavy rain caused subsidence of the road surface at Chuoi slope (section Km264+700), on National Highway 16, passing through Chau Kim commune.
Chuoi Slope is located on the National Highway in Chau Kim commune with a length of about 3 km, steep slope, many sharp turns. This is the main route connecting the center of Que Phong district to the communes of the Northwest cluster such as: Chau Thon, Tri Le, Quang Phong, Cam Muon, Nam Nhong and to the districts of Tuong Duong, Ky Son of Nghe An province.