Land clearance for Vinh - Cua Lo road project: People are allowed to choose resettlement land locations

Article: Tran Chau - Technique: Lam Tung DNUM_BCZAEZCABJ 09:36

(Baonghean) - Mr. Ha Thanh Tinh - Vice Chairman of Vinh City People's Committee said that the city will resolve this if the households of Nghi Duc commune volunteer to relocate early to give up land for the Vinh - Cua Lo road.

People are selected for resettlement land and receive an additional 18 million VND if they relocate early.

The meeting between city leaders and a large number of people in Nghi Duc commune on April 10, 2019 recorded hundreds of opinions about concerns and difficulties in the final stage of site clearance (GPMB) to serve the construction of Vinh - Cua Lo road.

Most people expressed their opinions about the resettlement land area, the price of the place of arrival and departure, how to make family life convenient when moving to the new place when there are still livestock and poultry... Some people said that dividing the land into plots of only 150m2/household as it is now is not suitable, resettlement area is slow, after receiving compensation, is it enough to build a house...

At the meeting, there were the attendance of comrade Nguyen Van Lu - Deputy Secretary of Vinh City Party Committee, Chairman of Vinh City People's Council; Le Quoc Hong - Head of Vinh City Party Committee's Mass Mobilization Committee and departments and offices of the city. The above opinions were fully explained by Vinh City Land Fund Center.

Đường 95 đoạn qua xóm Xuân Hương xã Nghi Đức (ảnh lớn). Khu tái định cư tại xóm Xuân Đồng và Khu tái định cư tại xóm Xuân Trung (xã Nghi Đức) đang được gấp rút hoàn thành. Ảnh: Lâm Tùng

Road 95 through Xuan Huong hamlet, Nghi Duc commune (large photo). The resettlement area in Xuan Dong hamlet and the resettlement area in Xuan Trung hamlet (Nghi Duc commune) are being urgently completed. Photo: Lam Tung

“Land recovery compensation also depends on whether the household has all or part of the land recovered, how much residential land area is recovered, and the number of households with registered residences living on that land.

If there are 200m2Residential land but only one household lives there, that household will be allocated a residential plot when being relocated; but if it is also 200m2"If a household has a child living on the same land, they will be allocated 2 lots," said Mr. Nguyen Tat Son, representative of Vinh City Land Fund Center.

The city has a compensation plan and announced and provided specific instructions for people subject to land acquisition. “The resettlement land fund of Xuan Dong hamlet is for households that register for resettlement in advance. If any household registers before April 30, there will be an additional support policy of 18 million VND/household for 4 or more people; and for households with 4 or less people, the support will be 12 million VND/household. This mechanism is in addition to the support policy of the province and we hope to speed up the progress compared to the plan,” Mr. Nguyen Tat Son affirmed.

Nghi Duc commune residents look at the compensation plan. Photo: Tran Chau

“If any family agrees to volunteer for land acquisition first, they will be able to choose a resettlement land location and the City Land Fund Center will consider resolving this issue.”

Mr. Ha Thanh Tinh - Vice Chairman of Vinh City People's Committee

Work without days off

In recent days, it can be said that many agencies and units related to land acquisition and clearance in Vinh city have not had a day off before the deadline for completing the work. City leaders have divided into many groups to go to the people to do mass mobilization work, directly solving difficulties.

The city has continuously organized two construction protection campaigns for the Vinh - Cua Lo road project and the 72m road connecting the old Quan Bau intersection and Xo Viet Nghe Tinh road, which has been congested for many years.

Các đơn vị thi công đường 72m đoạn Ngã 5 Quán Bàu - Đại lộ Xô Viết Nghệ Tĩnh. Ảnh: Lâm Tùng

Construction units of the 72m road at the Quan Bau intersection - Xo Viet Nghe Tinh Avenue. Photo: Lam Tung

Staff of the Vinh City Land Fund Center, the Department of Natural Resources and Environment, and the construction unit all worked on Saturdays and Sundays to check the origin, determine the time, advise on the issuance of a legal compensation plan, and urge the progress of the resettlement area construction. The above changes in the land acquisition work demonstrate the city's determination to ensure the progress of handing over clean land to investors before April 30, 2019.

According to the report, the project to build the Vinh - Cua Lo connecting road (phase 1) through Vinh city has currently received compensation for land acquisition and resettlement in Nghi Duc commune and is building a resettlement area in Xuan Trung hamlet. For the resettlement area in Xuan Dong hamlet, Nghi Duc commune (196 plots) has handed over the site for 178/196 plots and is continuing to direct the land acquisition for the remaining plots.

In Nghi Phu commune, the resettlement area of ​​Nghi Phu Primary School 2 has completed land acquisition. For the resettlement area in Hamlet 5, Nghi Phu commune, the plan is expected to be approved before March 25, 2019. The resettlement area in Hamlet 21 has inventoried 92/172 plots, and is continuing to mobilize the inventory of the remaining households.

Đường 72m đi qua điểm Trường Tiểu học 2 xã Nghi Phú. Ảnh: Lâm Tùng

The 72m road passes through Primary School 2 in Nghi Phu commune. Photo: Lam Tung

Regarding compensation for road construction site clearance: The section through Nghi Duc commune, 78 agricultural land plots, has handed over 68/78 plots, and is continuing to direct the clearance of the remaining plots. The residential land section is the most difficult part, and the price plan and compensation plan are being made public.

The whole political system actively participates.

Early this April, Mr. Tran Ngoc Tu - Chairman of Vinh City People's Committee chaired a working session to review the progress of compensation and support for site clearance of key projects and assign specific tasks to each project.

For the Vinh - Cua Lo road construction project (phase I), the city requires departments, offices, and the People's Committees of Nghi Phu and Nghi Duc communes to closely follow the tasks and progress assigned in Plan No. 201 of the Vinh City People's Committee and the conclusion of the Steering Committee to seriously and promptly implement them.

“The staff invested time, even working overtime, to be determined in performing their duties, focusing on clearing the 9m strip to clear the road. Any problems or difficulties during the implementation process must be reported and solutions proposed promptly.”

Mr. Tran Ngoc Tu - Chairman of Vinh City People's Committee.

The City Party Committee's Propaganda Department, the City Fatherland Front Committee and political organizations, the political system of wards and communes actively propagate and mobilize, the Finance - Planning Department advises the City People's Committee to approve land prices before April 8, 2019. Resolve complaints before April 15, 2019. Focus on promptly handling and removing difficulties and obstacles regarding land and land prices for each project according to the department's field.

Immediately after the land price is available, take the lead in coordinating with the City People's Committee's staff departments to announce relevant policies and regulations to coordinate with communes to hold land acquisition meetings on time. Vinh Investment and Construction Project Management Board speeds up the construction progress of projects: Nghi Phu Primary School, resettlement areas serving land acquisition for Vinh - Cua Lo road project (phase 2), to be completed before April 30, 2019, adjust the planning of resettlement areas when necessary; focus on completing the resettlement area of ​​Xuan Trung hamlet, Nghi Duc commune as soon as possible.

For the VSIP industrial park and urban area project in Hung Chinh commune, the city requested the Department of Natural Resources and Environment to advise on approving the compensation plan.

The Land Fund Development Center coordinates with the Investor and the People's Committee of Hung Chinh Commune to make payment and hand over the site before April 20, 2019. The People's Committee of Hung Chinh Commune confirms the origin of land use and the Land Fund Development Center develops a compensation plan, supports the appraisal, approval, and handover of the site before April 30, 2019.

The city also encourages and propagates, requests party members and people of the city to promote the sense of responsibility, make efforts to contribute to site clearance on schedule, which is also a positive contribution to building a modern civilized city.