Phase 1 of the Ban Mong reservoir project has reached 56% completion.

DNUM_AIZBCZCABF 19:01

(Baonghean.vn) – This is the data compiled by the Compensation, Support and Resettlement Council of Quy Chau district, up to the end of November 2015.

Phase I of the Ban Mong reservoir project includes auxiliary dams, Chau Binh drainage canals and reservoir channels with a total area to be recovered of 119 hectares. Up to now, Quy Chau has recovered and handed over the construction site in the area of ​​auxiliary dam 1, waste dumps No. 1, 2, 3, 4, 5, Chau Binh drainage canal from K0+000 to K8+108;... with a total area of ​​66.68 hectares, equivalent to 56%.

Kênh tiêu Châu Bình thuộc dự án hồ chứa nước bản Mồng được thi công.
Chau Binh drainage canal belongs to Mong village reservoir project under construction.

The progress of this land acquisition and clearance is assessed as not achieving the set plan's objectives. The reason is that during the process of implementing compensation and support, some households have not agreed with the unit price of land, trees, crops, and architectural works; at the same time, there are 28 households that have been producing stably for many years on the land area of ​​Co Ba Forestry, so it is difficult to prepare compensation and support records for land acquisition and clearance;...

On the other hand, the budget for compensation and support is still lacking. Up to now, the Compensation, Support and Resettlement Council of Quy Chau district has prepared compensation records for 455/531 affected households and approved compensation, support and resettlement plans for 368 households with a total budget of 100.12 billion VND. However, the total payment amount has only been over 88 billion VND, still lacking nearly 12 billion VND.

Nhiều hộ dân đã xây dựng lại nhà ở theo hình thức xen dắm sau khi nhận được tiền đền bù.
The family of Mr. Nguyen Tran Luyen, Quynh 2 village, Chau Binh commune (far right) rebuilt their house in a mixed-use style after receiving compensation.

Currently, the district is focusing on synchronous solutions to speed up the progress of site clearance and compensation; at the same time, implementing steps to build infrastructure for resettlement areas for affected households that must be relocated, striving to complete in 2016.

Thanh Duy

RELATED NEWS

Featured Nghe An Newspaper

Latest

x
Phase 1 of the Ban Mong reservoir project has reached 56% completion.
POWERED BYONECMS- A PRODUCT OFNEKO