Nghe An: Consideration of rural traffic cement support mechanism for localities with special conditions
(Baonghean.vn) - Voters' recommendation: Providing cement support to communes that register to finish within the year and providing 1,050 tons/commune equally is not reasonable. We suggest that the province give loans to communes with large areas and many kilometers of road to be built 2 years in advance and in larger quantities to reduce the investment burden on the people.
![]() |
Building rural roads in Nam Anh (Nam Dan) |
Regarding this issue, the relevant authorities responded as follows:
Pursuant to Resolution No. 166/2015/NQ-HDND dated July 10, 2015 on ''encouraging and supporting policies in the construction of new rural areas in Nghe An province in the period of 2015-2020'' and Decision No. 48/2015/QD-UBND dated August 31, 2015 of the Provincial People's Committee ''on promulgating Regulations on encouraging and supporting policies in the construction of new rural areas in Nghe An province in the period of 2015-2020'', which stipulates:
Arrange cement support level for communes registered to meet standards in 2016 with the quantity to be implemented as follows:
+ 6 km/commune for plain communes
+ 8 km/commune for communes of 6 mountainous districts
Mountainous communes that register to meet NTM standards will be supported with 1,400 tons of cement, and delta communes that register to meet standards will be supported with 1,050 tons of cement to build rural roads.
![]() |
Thanks to the support of cement, people in Quynh Bang and Quynh Luu have started to build rural roads, illustration photo, Thu Huyen |
Communes that did not register but still met the standards in 2016 will still receive the same support as registered communes. Thus, the voters' request to lend 2 years in advance to communes with large areas and many kilometers of roads to be built and in larger quantities to reduce the investment burden on the people has not been implemented because it is not in accordance with the province's policy.
![]() |
Thanks to the complete transportation system, people in village 11, Hoa Son commune (Anh Son) have great convenience in transporting rice during the harvest season. |
Regarding some localities with special conditions, requesting additional cement support, in the coming time, the Department of Agriculture and Rural Development will synthesize and advise the Provincial People's Committee to consider and decide.
For loan requests prior to 2 years: VIn early January every year, the Provincial People's Committee approves the list of communes registered to meet NTM standards, which is the basis for supporting cement according to the above policy. Therefore, there is no basis for lending to communes 2 years in advance.
PV (TH)