(Baonghean.vn) - In order to quickly put the Nghi Thiet Cement Grinding Station and Port Cluster (Nghi Loc - Nghe An) into operation, The Vissai Cement Group requires contractors to mobilize human resources and construction equipment 24/24 hours a day. Therefore, in the first days of the new year 2017, the construction site cluster in Nghi Thiet is always bustling with 7 contractors and nearly 700 workers.
 |
Nghi Thiet wharf (Nghi Loc - Nghe An) 2,000 m long is being accelerated. |
 |
Although the weather at sea was unfavorable, contractors mobilized human resources and construction equipment to work in 3 shifts a day to complete the project soon. |
 |
Nghi Thiet sea area has a natural depth of 9m, when completed, Nghi Thiet Port will serve ships of over 70,000 tons to load and unload goods. Initially, it will serve the export of cement and clinker of Song Lam Cement Factory, in the long term the port will be upgraded to an international port for the entire North Central region. |
 |
Onshore, the Cement Grinding Station and the 3,000m long conveyor belt connecting the seaport are also speeding up construction progress. |
 |
Contractors' workers are mobilized to work 24/7, including holidays. In the photo, workers are constructing the Nghi Thiet cement grinding station area. |
 |
Construction area of Nghi Thiet Cement Grinding Station. |
 |
The team of workers is completing the stages of the Cement Grinding Station. |
 |
The entire Nghi Thiet Cement Grinding Station and Seaport cluster is planned to be put into use in the second fund year of 2017. |