Funds have been paid for site clearance for the Hanh Dich - Muong Dan road project after 8 years of delay.

Gia Huy DNUM_DBZABZCABJ 17:13

(Baonghean.vn) - That is the information that Que Phong District People's Committee responded regarding the Hanh Dich - Muong Dan traffic project.

Nghe An Newspaper issued on December 26, 2018 and baonghean.vn on December 31, 2018 published the article“Nghe An: Road completed 8 years ago, people have not received compensation yet”The Hanh Dich - Muong Dan traffic route (Hanh Dich commune, Que Phong) was completed and put into use in 2010, but after 8 years, dozens of households here have not received full compensation even though they had previously given up their land to carry out the project.

Tuyến đường mặc dù hoàn thành đã 8 năm nhưng đến nay vẫn còn 24 hộ chưa nhận đầy đủ tiền đền bù. Ảnh: P.B
Although the road was completed 8 years ago, there are still 24 households that have not received full compensation. Photo: Archive

After the newspaper reported, on January 29, 2019, the People's Committee of Que Phong district issued Official Dispatch No. 98/UBND-TCKH to respond to the issue raised by the newspaper, in which it affirmed: The fact that Nghe An Newspaper reported that the Road project was completed 8 years ago and people have not received compensation is true.

The Hanh Dich - Muong Dan traffic project was invested by the Provincial People's Committee in Decision No. 4855/QD-UBND dated December 17, 2004 with a total investment of 27.5 billion VND from JICA (Japan) and the provincial budget, assigned to the Que Phong District People's Committee as the investor. The project was implemented and completed and put into use at the end of 2010. During the project implementation, 135 affected households had to pay compensation for site clearance with a total cost of 1.475 billion VND, however, up to now, the project has only been allocated 620 million VND for site clearance.

Trên tuyến đường, nhiều điểm đã hư hỏng, xuống cấp. Ảnh: P.B
On the route, many points are damaged and degraded. Photo: PB
The fact that the Muong Dan - Hanh Dich traffic route was completed in 2010 but has not been allocated enough land acquisition funds as reported by Nghe An Newspaper is due to the fact that in recent years, the district budget has encountered many difficulties, the local revenue is low and not enough to balance expenditures, the budget is mainly focused on implementing social security tasks, unexpected tasks, epidemics... so the land acquisition funds have not been promptly arranged to pay the people.

However, at the end of 2018, the District People's Committee thoroughly saved expenses to prioritize support for land acquisition and clearance expenses and on December 28, 2018, issued Decision No. 297/QD-UBND on settling the 2018 budget to support payment for land acquisition and clearance for the Hanh Dich - Muong Dan Traffic Road project, the amount of VND 855,745,000. Currently, the Que Phong District People's Committee has directed the Land Acquisition and Clearance Council to carry out procedures to withdraw resources to pay for the people./.