Lach Van Bridge closing project of Nghi Son Coastal Road (Thanh Hoa) to Cua Lo (Nghe An)

Thanh Le July 26, 2023 12:27

(Baonghean.vn) - Lach Van Bridge is located at Km48+850 in Dien Kim and Dien Thanh communes, Dien Chau district, with a length of 755m, including 17 spans, of which 3 are balanced cantilever spans and 14 are Super T girder spans, with a bridge width of 12m.

On July 26, the Department of Transport held a closing ceremony for Lach Van Bridge under the Coastal Road Project from Nghi Son (Thanh Hoa) to Cua Lo (Nghe An), section Km7 - Km76.

Attending the ceremony were comrades: Le Hong Vinh - Member of the Provincial Party Standing Committee, Permanent Vice Chairman of the Provincial People's Committee; Hoang Phu Hien - Member of the Provincial Party Executive Committee, Director of the Department of Transport.

bna_lễ hợp long. anh thanh le.jpeg
Delegates held the closing ceremony of Lach Van Bridge Project. Photo: TL

The Coastal Road Project from Nghi Son (Thanh Hoa) to Cua Lo (Nghe An) section Km7 - Km76 has been approved by the Provincial People's Committee in Decision No. 2925/QD-UBND dated August 13, 2021, with a total investment of VND 4,651 billion (central budget VND 3,200 billion, local budget VND 1,451 billion). Total length 64.46 km (Hoang Mai town 9.78 km; Quynh Luu district 16.41 km; Dien Chau district 24.41 km; Nghi Loc district 13.64 km, Cua Lo town 0.22 km).

bna_thi công. ảnh thanh lê.jpeg
After closing, the construction unit will complete Lach Van bridge. Photo: TL

The project has an investment scale: The route is designed according to the standards of a grade III plain road; there are 8 bridges, of which, there are 5 large bridges (Hoang Mai, Lach Quen, Cua Thoi, Lach Van, Nghi Quang) and 3 small bridges (Tan Long, Nha Le canal, Nghi Tan).

Lach Van bridge at Km48+850 in Dien Kim and Dien Thanh communes, Dien Chau district, has a length of 755m, including 17 spans, of which 3 are balanced cantilever spans and 14 are Super T girder spans, the bridge width is 12m, constructed by Tan Nam Construction Joint Stock Company.

The project has been under construction since February 2022 and is now in the final stages of completion, expected to be completed in September 2023, with a construction progress of 19 months, 17 months ahead of schedule.

bna-toàn cảnh. ảnh thanh lê.jpeg
Lach Van Bridge is 17 months ahead of schedule. The closing ceremony of Lach Van Bridge is an important milestone in the project's construction process, connecting the main span of the bridge. Photo: TL

This is a project within the overall planning of Vietnam's coastal roads approved by the Prime Minister in Decision No. 129/QD-TTg dated January 18, 2010 and adjusted in Decision No. 1516/QD-TTg dated November 4, 2019.

The project will be implemented from February 2022 with a contract schedule of 48 months. However, Nghe An Department of Transport has directed the development of an implementation plan: For the bridge section, it will be completed within 24 months (February 2024); for the route section, it will be completed within 30 months (quarter II/2024).

bna_trao quà. ảnh thanh lê.jpeg
Standing Vice Chairman of the Provincial People's Committee Le Hong Vinh and leaders of the Department of Transport gave gifts to encourage workers at the construction site. Photo: TL

Currently, the Department of Transport is resolutely directing construction units to focus on accelerating the construction progress of roadbeds, foundations, bridges and works on the route, and deploying asphalt concrete paving for 10 km. The construction and installation value is about 1,737 billion VND, reaching 63% of the contract (22% higher than the contract progress). It is expected that in 2023, 6 bridges will be completed and about 42 km of asphalt concrete will be paved.

bna_công nhân. ảnh thanh lê.jpeg
Standing Vice Chairman of the Provincial People's Committee Le Hong Vinh and leaders of the Department of Transport presented gifts to the construction unit. Photo: TL

Up to now, 2,843,141 billion VND has been arranged (2,180 billion VND from the central budget, 663,141 billion VND from the local budget). Of which, the capital source in 2023 is 980 billion VND (730 billion VND from the central budget, 250 billion VND from the local budget); the disbursed capital source in 2023 is 430.7 billion VND, reaching 44% of the arranged capital source (reaching 52% of the public investment capital).

Regarding site clearance, 54.58 km/59.91 km of the site has been handed over, reaching 91%. Of which: Hoang Mai town handed over 8.6 km/9.42 km, reaching 91%; Quynh Luu district handed over 14.2 km/16.17 km, reaching 88%; Dien Chau district handed over 23.9 km/24.44 km, reaching 98%; Nghi Loc district handed over 7.7 km/9.66 km, reaching 80%; Cua Lo town handed over 0.18 km/0.22 km, reaching 82%. It is expected to complete and hand over the entire site in 2023.

bna_giám sát. ảnh thanh lê.jpeg
Provincial leaders gave gifts and encouraged the consulting and monitoring unit. Photo: TL

The investment in building the route aims to exploit and effectively use marine and coastal resources, serve the socio-economic development of coastal localities, and strengthen the province's national defense and security.

At the same time, it contributes to improving the transport network of the province and regions, shortening travel time between economic zones, tourist areas, especially sea tourism, as well as serving rescue work, handling situations in response to natural disasters and climate change.

bna_thi cong. anh thanh le.jpg
The Department of Transport is directing contractors to focus on human resources and vehicles to speed up the project's construction progress. Photo: TL

The leader of the Department of Transport said that in order to ensure construction progress and disbursement of 100% of allocated capital, in the coming time, localities will focus on directing, removing difficulties and obstacles, and speeding up site clearance progress so that construction units can ensure project progress.

bna_thảm. ảnh thanh lê.jpeg
Currently, 10 km of asphalt concrete is being laid on the route. Photo: TL

For the investor (Nghe An Department of Transport), we are focusing on directing contractors to continue to increase human resources and means to speed up progress in order to strive to complete the project and put it into use according to the set schedule.

Featured Nghe An Newspaper

Latest

Lach Van Bridge closing project of Nghi Son Coastal Road (Thanh Hoa) to Cua Lo (Nghe An)
POWERED BYONECMS- A PRODUCT OFNEKO