An Hung Garment Factory (Nghe An) is ready to go into operation.
(Baonghean.vn) - The An Hung Garment Factory Project (Yen Thanh District, Nghe An) is one of the province's key projects in Cong Thanh Commune, Yen Thanh. After a period of active construction, the factory has basically completed all construction items and is ready to go into operation in early 2021.
At this time, on the Project siteAn Hung Garment FactoryIn Cong Thanh commune, Yen Thanh district, it is becoming very busy, hundreds of workers and machinery are actively working to ensure progress on the 7th day of Lunar New Year 2021, the factory will go into operation.
The An Hung Garment Factory Project in Cong Thanh Commune, Yen Thanh has a total investment of over 600 billion VND, designed to be over 10 hectares wide. The factory started construction in January 2020. This is the largest garment factory in Yen Thanh district, invested synchronously on a modern scale with production lines and equipment imported from abroad.
![]() |
An Hung Garment Factory in Cong Thanh Commune, Yen Thanh has completed over 95% of the work volume. Photo: Van Truong |
A representative of An Hung Garment Factory said: An Hung Garment Factory started construction in January 2020, but encountered many difficulties such as the outbreak of Covid-19, the factory had to temporarily stop construction. Thanks to the efforts of the investor, the contractor and hundreds of workers working in 3 shifts, after only nearly 10 months of construction, the project has now completed more than 95% of the work.
Currently, the roof of the factory system covering an area of over 23,000 m2 has been completed.2, 6,000 m2 dining system2Currently, the project is completing auxiliary items such as internal roads, lighting, ventilation fans. Speeding up the construction progress of warehouses and houses. Expected to be completed and put into use in early 2021.
![]() |
The factory area is ready for assembly of equipment lines. Photo: Van Truong |
In addition to the construction, the An Hung Garment Factory project has also coordinated with related sectors to recruit over 3,500 workers. Garment workers at the factory will receive a fairly high salary of 6-8 million VND/person/month.
Vocational training will be free, provided with labor protection equipment and tools, covered by social insurance and health insurance, enjoy bonuses, annual leave and other benefits according to regulations of the State and the company...
![]() |
Installing light bulbs in the workers' canteen area. Photo: Van Truong |