Economy

After 8 years, the industrial park in Quynh Luu district has only completed the road.

Tien Dong DNUM_DBZBCZCACE 09:46

After 8 years since completing investment procedures, Quynh Chau Industrial Park (Quynh Luu) has only completed the entrance road.

Quynh Luu: After 8 years, the industrial park has only completed the road. Video: Tien Dong
bna_23.jpg
Quynh Chau Industrial Cluster was submitted by Quynh Luu District People's Committee to the Provincial People's Committee for implementation in 2016. After being appraised by the Department of Construction, on January 12, 2017, the Provincial People's Committee issued Decision No. 178/QD-UBND approving the detailed construction plan at a scale of 1/500 for this industrial cluster. In the photo: Signpost to Quynh Chau Industrial Cluster. Photo: Tien Dong
bna_13.jpg
Accordingly, this industrial cluster is located in Quynh Chau commune (Quynh Luu), in Khe Sau hill area. This is a concentrated industrial cluster of Quynh Luu district, with synchronous infrastructure construction to arrange small and medium-sized industrial enterprises, attracting investment for economic development in the area. Photo: Tien Dong
bna_9.jpg
According to the plan, Quynh Chau Industrial Cluster has a total area of ​​70 hectares, divided into 4 functional areas, including: Industrial cluster management and operation center area; land for construction of factories and enterprises; technical infrastructure area; green area combined with forestry land. Photo: Tien Dong
bna_26.jpg
The total expected construction investment of this industrial cluster is more than 414 billion VND, with many items such as: leveling, water supply, drainage, electricity supply, and communication system. Photo: Tien Dong
bna_18.jpg
However, it has been nearly 8 years since the planning was approved, and to date, the People's Committee of Quynh Luu district has only completed a 900m long road to the industrial park, while the surrounding area is still covered with vast acacia and cajuput hills. Photo: Tien Dong
bản đồ quy hoạch
Map of traffic system planning and red line boundaries, construction boundaries of Quynh Chau Industrial Park (Quynh Luu). Photo: Tien Dong
bna_24.jpg
According to the representative of the People's Committee of Quynh Luu district, due to lack of funding, the construction of infrastructure for this industrial cluster cannot be implemented as expected. Currently, the district is calling for investors to implement the infrastructure construction. After having investors, the next steps such as site clearance and construction of new functional subdivisions will be carried out. Photo: Tien Dong