(Baonghean.vn) - On the morning of August 17, the Steering Committee for Land Acquisition and Resettlement of Vinh City held a working session to evaluate the implementation results and some problems regarding compensation for land acquisition and resettlement at the Vinh - Cua Lo 95m road construction project; the Quang Trung B area renovation project and some construction packages of the Vinh Urban Development Sub-project.

Comrade Vo Viet Thanh - Member of the Provincial Party Standing Committee, Secretary of Vinh City Party Committee chaired the meeting.

Currently, compensation, support for site clearance and resettlement are being implemented, however the implementation process still faces many difficulties.

In the Vinh - Cua Lo project section through Nghi Phu and Nghi Duc communes, 266 agricultural plots and 197 households with residential land and garden land were affected. The work of confirming the origin of land use and the inventory process is still stuck due to the lack of cooperation of some households and cooperatives; The construction of resettlement areas still faces many difficulties.

Xây dựng đường nối QL 46 với đường ven Sông Lam, Tiểu dự án phát triển đô thị Vinh. Ảnh: Võ Huyền
Construction of the road connecting National Highway 46 with the Lam River coastal road, Vinh Urban Development Sub-project. Photo: Vo Huyen

For the Quang Trung B area renovation project, there are 421 households that need to be cleared. Currently, the city has completed the compensation plan, support for clearance and resettlement. It is expected that the inventory, counting of assets and the preparation of compensation plans and payment of clearance support money will be completed by the end of this year. However, kThe immediate difficulty is arranging temporary accommodation for people when dismantling housing projects.

In the Vinh urban development sub-project, in the Hung Tay - Vinh road construction package, there is still a drainage ditch item (arising) that has not yet completed the confirmation of land use origin of 25 households; in the road construction package connecting National Highway 46 with the Lam River road, there is still 1 household that does not accept compensation and support according to the approved plan, affecting the overall progress of the project.

Overview of the working session. Photo: Vo Huyen

Concluding the meeting, the Secretary of the City Party Committee emphasized that these are key projects of the city. Therefore, Party committees at all levels and the entire political system need to take drastic action; at the same time, assign specific responsibilities to each member of the steering committee, units, wards and communes.

For Quang Trung B area, it is necessary to complete the procedures and policies to soon develop a compensation plan and support for site clearance; contact the people to find temporary housing.

The 95m Vinh - Cua Lo road project needs to speed up progress, complete resettlement areas to ensure quality infrastructure and urban aesthetics. With nHouseholds and cooperatives that do not cooperate will be subject to compulsory inventory; strive to complete land acquisition and clearance by the end of 2018.

It is necessary to completely resolve the remaining related problems of the Vinh Urban Development Sub-project to complete the project on schedule as committed by the sponsor by the end of this year./.