Vinh City speeds up site clearance progress for Vinh - Cua Lo project
(Baonghean.vn) - On the afternoon of November 6, the Steering Committee for compensation and support for land acquisition and resettlement in Vinh City held a meeting to inspect the compensation, support for land acquisition and resettlement for the Vinh - Cua Lo road project and a number of key projects of the province.
Comrade Vo Viet Thanh - Member of the Provincial Party Committee, Secretary of Vinh City Party Committee chaired the meeting.
The Vinh - Cua Lo road project passing through Nghi Duc and Nghi Phu communes (Vinh City) is 3.4km long, and has handed over 1.2km of agricultural land through Nghi Duc commune, with 2.2km remaining. Currently, there are still problems: garden land, residential land 1.3km with 197 households; agricultural land 0.7km with 266 plots and cemetery land 0.2km with 82 graves.
![]() |
The Steering Committee for compensation and support for land acquisition and resettlement in Vinh City held a meeting to inspect the compensation, support for land acquisition and resettlement for the Vinh - Cua Lo road project. Photo: Vo Huyen |
The city has approved the compensation and support plan for land acquisition for 112/197 households with garden land, residential land and 143/266 agricultural land plots. Currently, the land acquisition work is facing many difficulties in confirming the origin of land use, inventorying assets, making compensation plans, supporting land acquisition and resettlement. Most households do not cooperate in the inventory and counting process, do not agree with the compensation and support plan for land acquisition and resettlement, and have not agreed to receive money and hand over the site.
![]() |
Asphalt pavement on Vinh - Cua Lo route. Photo: Viet Phuong |
For some other key projects such as the project to upgrade and renovate area B - Quang Trung Apartment Complex; VSIP industrial and urban area project; Vinh airport upgrade and expansion project, the city is currently focusing on implementing them under the direction of the Provincial People's Committee.
At the meeting, after listening to recommendations, proposals as well as difficulties and obstacles, Comrade Vo Viet Thanh - Secretary of Vinh City Party Committee requested units, wards and communes to focus more on site clearance work, to ensure the progress as required by the Provincial People's Committee. At the same time, carry out the construction of resettlement areas in a synchronous manner to arrange resettlement for people after land acquisition.