Vinh City and Hung Nguyen must hand over the site for VSIP project before April 30, 2019.

Pearl DNUM_CJZADZCABJ 07:38

(Baonghean.vn) - That was the direction of Chairman of the Provincial People's Committee Thai Thanh Quy at the recent meeting to urge key projects.

VSIP Industrial Park and Urban Area project through Hung Chinh area (Vinh city) 27 hectares; currently the city has handed over 21 hectares to the investor, 6 hectares remaining. Meanwhile, in Hung Nguyen, there are still problems with the stadium, land area for the industrial park...

After listening to the investor's opinion, Chairman of the Provincial People's Committee Thai Thanh Quy requested Vinh city to complete site clearance for the VSIP (Hung Chinh) project before April 30, 2019.

For the Urban Area Phase 2A, 2B, 3, the Chairman of the Provincial People's Committee also requested relevant departments and branches to closely coordinate with the investor to carry out procedures to clear the land for the Urban Area Phase 2A.2, 2B, 3 and the Industrial Park Phase 2 with a total area of ​​about 259.32 hectares in Hung Nguyen town, Hung Tay commune, Hung Dao commune of Hung Nguyen district and Hung Chinh commune of Vinh city to hand over the land before August 2019.

VSIP Nghe An urban area is facing problems with land clearance. Photo: Tran Chau

For Hung Nguyen district, the Chairman of the Provincial People's Committee assigned the district to focus on resolving issues related to the Hung Tay commune stadium, some land plots belonging to Mr. Thu and Mr. Giao's households in Bac Phuc Hoa hamlet and the Women's Union of Khoa Da 3 hamlet located in the phase 1A industrial park so that VSIP can soon start construction and hand over land to investors.

For Industrial Park phase 1B, hand over clean site before April 30, 2019.

For households in Hung Chinh commune who are encroaching on land in Hung Nguyen town, the People's Committee of Hung Nguyen district is requested to hand over the cleared land to VSIP before April 30, 2019.

For Urban Area Phase 2A.2, 2B, 3 and Industrial Park Phase 2, it is recommended that the People's Committee of Hung Nguyen district direct the acceleration of site clearance progress to hand over before August 2019.

Talking with Mr. Nguyen Tat Son - Director of Vinh City Land Fund Center, he said: Currently, the area that needs to be cleared for the VSIP project is 6 hectares of agricultural land, Hung Chinh commune is publicly disclosing the land origin to the people. After the disclosure, the Center will establish a compensation plan for the city to review and proceed with compensation for the people. We commit to handing over the land to the investor by the above deadline.

It is known that the compensation price for 1 hectare of agricultural land in Hung Chinh for this project is 112,500,000 - 127,500,000 VND/sao.

Featured Nghe An Newspaper

Latest

x
Vinh City and Hung Nguyen must hand over the site for VSIP project before April 30, 2019.
POWERED BYONECMS- A PRODUCT OFNEKO