In 7 days, Nghe An started construction on 1,624 houses and completed and handed over 523 houses to the poor.

Plum Blossom DNUM_CHZADZCACF 21:09

Within 7 days, from March 20 to 27, 2025, Nghe An province continued to start construction on 1,624 houses and completed and handed over 523 houses to the poor.

 Cán bộ Mặt trận huyện Yên Thành và xã Long Thành kiểm tra tiến độ xây dựng nhà ở cho người có hoàn cảnh khó khăn t
Construction of houses for people with housing difficulties in Long Thanh commune, Yen Thanh district began. Photo: Mai Hoa

Continuing to implement the program of mobilizing and supporting the construction and repair of houses for the poor and people with housing difficulties in the province according to Directive No. 21, dated February 10, 2023 of the Standing Committee of Nghe An Provincial Party Committee (Program 1838); at the same time, implementing the program of supporting the elimination of temporary and dilapidated houses according to the call of Prime Minister Pham Minh Chinh, all levels, sectors and localities in Nghe An have taken drastic action with very specific goals and targets set.

Many creative ways of mobilizing and integrating resources have been deployed at all levels to accelerate the implementation of housing support programs for people with revolutionary contributions; support housing according to national target programs and eliminate temporary and dilapidated houses for households not belonging to the above two groups.

b203a2e7b2d902875bc8.jpg
Chart: Within 7 days, from March 20 to 27, 2025, the whole province started construction of 1,624 houses. Graphics: Huu Quan

As a result, from March 20 to 27, 2025, the province started construction of 1,624 more houses (745 new houses, 879 repaired houses). Of which, the source from the 2 National Target Programs is 588 houses (205 new houses, 383 repaired houses); the source from the Housing Support Program for Meritorious People is 400 houses (168 new houses, 232 repaired houses); the source from the socialized Program 1838 of the province is 636 houses (372 new houses, 264 repaired houses).

Also within 7 days, from March 20 to 27, 2025, the whole province had 523 more houses completed and handed over for use (203 newly built houses, 320 repaired houses). Of which, the source from 2 National Target Programs is 209 houses (76 newly built houses, 133 repaired houses); Housing support program for people with meritorious services is 31 houses (06 newly built houses, 25 repaired houses); Program 1838 is 283 houses (121 newly built houses, 162 repaired houses).

2bd8903d8003305d6912.jpg
Chart: Within 7 days, from March 20 to 27, 2025, the whole province completed and handed over 523 houses. Graphics: Huu Quan

Cumulatively from the beginning of the Program to date, the whole Nghe An province has completed and handed over 13,527 houses to those in need of housing (10,576 newly built houses, 2,951 repaired houses). Of which, the source from the 2 National Target Programs is 4,924 houses (3,187 newly built houses, 1,737 repaired houses); the Housing Support Program for Meritorious People is 86 houses (26 newly built houses, 60 repaired houses); the Support Program from socialized sources is 8,517 houses (7,363 newly built houses, 1,154 repaired houses).

Through reviewing, updating, and supplementing housing needs in localities from March 6 to 27, 2025, the total need for support in building and repairing houses in the 2023-2025 period has decreased compared to the previous review results; from 21,770 households (as of March 6, 2025), there are now 21,033 units (14,547 newly built units, 6,486 repaired units), a decrease of 737 units.

 MH, Ngôi nhà mới của gia đình chị Nguyễn Thị An, xóm 9, xã Quỳnh Lâm, huyện Quỳnh Lưu vừa hoàn thành, bàn giao ngày 1:2:2024. Ảnh Mai Hoa
Inauguration and handover of the new house of Ms. Nguyen Thi An's family, hamlet 9, Quynh Lam commune, Quynh Luu district. Photo by Mai Hoa

Thus, compared with the total demand and the number of implemented results, the total number of houses that need to be completed by August 31, 2025 in the whole province is 7,749 (4,176 new houses, 3,573 repaired houses). Of which, the source from the Housing Support Program for people with revolutionary contributions is 3,605 houses (1,899 new houses, 1,706 repaired houses); the source2 of the National Target Program is 1,674 houses (739 new houses, 935 repaired houses); the socialized source program is 2,227 houses (1,333 new houses, 894 repaired houses).

Within 7 days, from March 20 to 27, 2025, the provincial and district levels received socialized resources from organizations and individuals to support housing construction for the poor and households with difficult housing circumstances with a total of 1,397 million VND; of which the provincial level received 120 million VND and the district level received 1,277 million VND. The disbursement cost from the Program to eliminate dilapidated houses from socialized sources is 1,429 million VND.

 MH 16
Thong Tan Commune (Hung Nguyen District) mobilized the entire political system and people to participate in building houses for the people. Photo: Mai Hoa

The program of building houses for the poor and households with difficult housing conditions is being promoted by the Party Committees, authorities and the entire political system of Nghe An province to ensure social security, help poor and near-poor households and families with especially difficult circumstances have stable housing, improve the quality of life; at the same time, promote the implementation of the program of building new rural areas and civilized urban areas in localities.