Building a team of staff to meet development requirements

DNUM_BBZBBZCABF 14:37

(Baonghean) - The "Party Dialogue" column had an interview with comrade Le Tien Tri, Provincial Party Committee member, Secretary of Thai Hoa Town Party Committee on further strengthening the role of the Party Committee in leading investment attraction as well as speeding up the progress of key projects and works in the area.

Reporter:Recently, the Standing Committee of Thai Hoa City Party Committee has paid great attention to leading and closely directing key projects in the area, thereby actively contributing to speeding up the progress as well as improving the quality of each project. Could you please elaborate on this issue?

Comrade Le Tien Tri:The Town Party Committee has requested the Town People's Committee to direct the Project Management Board and relevant functional departments to urge, direct and create all favorable conditions for procedures according to regulations so that construction units can properly implement the contract and complete the items and sections of the project on schedule. Thanks to that, many works and projects have been accelerated, some backlogs have been resolved such as: handling the environmental pollution area in Hoa Hieu ward; repairing and upgrading the town's martyrs' cemetery; completing and putting into use according to the investment phase of works such as: Internal roads and embankments of Bau Sen park; Traffic road to the center of Nghia Hoa commune has completed the section connecting to the intersection with National Highway 48; The main road has completed the handover of the remaining households on the route, completed the longitudinal drainage ditch; N2 crossroad has completed the laying of base B on the entire route; N6 crossroad phase 1 has completed the items: assembling curbs, paving sidewalks and lighting. The D1 longitudinal axis route has completed the handover of the land at the production land of the remaining households on the route and completed the roadbed items to ensure the route is clear from the headquarters of Long Son Ward People's Committee to the intersection of N1 crossroad...

Lãnh dạo Thị xã Thái Hòa kiểm tra tiến độ thi công dự án khu thương mại dịch vụ Giốc Gạo Đồng Lầy
Thai Hoa Town leaders inspect the construction progress of the Goc Gao Dong Lay commercial service area project

The project “Conference center, wedding party and restaurant, hotel” in Dong Lay commercial and general service area is a key project in the field of trade and service. It has also completed the project items, has a business organization plan to ensure sufficient conditions to serve the successful organization of the 2nd Town Party Congress, term 2015 - 2020 at the end of July and is currently organizing business and service activities well.

At the same time, the Standing Committee, the Standing Committee of the Town Party Committee and the leaders of the Town People's Committee have focused on leading, directing and mobilizing the strength of the entire political system from the town to the grassroots, of the business community and the majority of people to agree and actively support the movement of building new rural areas and building civilized urban areas. Up to now, Thai Hoa has 6/6 communes meeting new rural standards, 2/4 wards are completing the criteria for wards meeting civilized urban standards.

Lãnh đạo Thị xã Thái Hòa chỉ đạo bảo vệ thi công tuyến đường vào trung tâm xã Nghĩa Hòa
Thai Hoa Town leaders direct security to construct the road to the center of Nghia Hoa commune

However, if assessed overall, there are still many projects in the area that are behind schedule compared to the committed schedule. This affects the completion of basic conditions for socio-economic infrastructure, especially industrial park infrastructure, and urban infrastructure is not synchronized, thus affecting the work of attracting investment to the area. Large production and business projects that have a spillover effect and promote economic development of the Town have not been attracted.

Reporter:Despite close leadership and direction, key projects and works in the area are generally behind schedule. What is the reason, comrade?

Comrade Le Tien Tri:If we evaluate fairly, in the recent past, administrative reform, discipline and administrative discipline in the Town have been directed and have had positive changes, but the results achieved have not met the development requirements of the Town, especially administrative procedures in granting land use right certificates, compensation for site clearance, attracting investment, and solving problems for businesses and people. However, the public ethics, sense of responsibility, and initiative in work, professional capacity and administrative skills of a number of cadres, civil servants and leaders in a number of departments, offices and branches have not met the requirements; the spirit of cooperation and collaboration between units and localities in solving some problems has not been truly responsible; the spirit of initiative, daring to think, daring to do, daring to take responsibility of the staff is still limited. The application of information technology in management, operation and solving administrative procedures has been slow and ineffective.

Reporter:To further strengthen the leadership and direction of Party committees from the Town to the grassroots level for projects and works in the area, in the coming time, how will the Standing Committee of Thai Hoa Town Party Committee identify key issues that need to be focused on directing and organizing implementation?

Comrade Le Tien Tri:In the immediate future, it is still necessary to focus on leadership and close direction for the construction of key works and projects in the area. In the long term, the Town Party Committee has clearly identified its leadership and direction viewpoint: to effectively carry out the task of economic development, it is necessary to focus on improving the investment and business environment, increasing investment attraction and developing enterprises; but the key is still the work of cadres, it is necessary to have a team of cadres and civil servants who meet the requirements of development. Therefore, in the Action Program of the Town Party Committee Executive Committee, term II, 2015 - 2020, the Party Committee Executive Committee plans to issue: 01 resolution on improving the investment and business environment, increasing investment attraction and developing enterprises; 01 resolution on cadre work and management of civil servants and public employees.

Thi công tuyến đường trọng ddiemr của Thị xã
Construction of key roads of the Town

The purpose of the resolution is to build a team of cadres, civil servants and public employees with a sense of responsibility and initiative in their work, with professional capacity and administrative skills to meet task requirements; proactively cooperate and collaborate in solving work; a team of leaders and managers with an aggressive mindset, daring to think, daring to do, daring to take responsibility.

Reporter:Thank you comrade!