Due to the lack of land for leveling, the 3rd project of the National Target Program of Quy Chau district is at risk of being 'frozen'.

Nhat Lan DNUM_CAZBBZCACC 06:59

(Baonghean.vn) - Quy Chau is currently focusing on implementing public infrastructure projects under the 3 National Target Programs. However, the projects under these programs all require land for leveling and filling. Although 4 land mines have been planned in Quy Chau district in Chau Binh, Chau Tien, Chau Phong, and Chau Thang communes, sadly no organizations or individuals dare to apply for mining licenses, despite the encouragement and appeals from the Party Committee and authorities. The reason is that Quy Chau district and neighboring localities have a low number of projects requiring land for leveling and are unable to recover capital. This is a truly difficult problem that needs to be resolved so that this locality can complete the projects of the 3 National Target Programs in the period of 2021 - 2025.

Some images of construction works and projects in the districtQuy ChauWaiting for land to be leveled, recorded by Nghe An Newspaper reporter on November 18, 2022.

The Chau Thang commune spillway is both narrow and low, so whenever there is prolonged heavy rain and the hydroelectric plant releases floodwaters, it sinks deep into the water, causing local isolation of residential areas. In the photo: During the floods in late September and early October 2022, the Quy Chau District Disaster Prevention and Control Command had to place signs prohibiting people and vehicles from crossing the Chau Thang suspension bridge. Photo: Vi Trang

The Chau Thang permanent rigid bridge project has been launched, expected to be completed by September 2025, replacing the old spillway bridge, fulfilling the goal of developing a synchronous and modern traffic infrastructure, ensuring technical infrastructure conditions, contributing to facilitating socio-economic development, ensuring security and defense for Quy Chau district. In the photo: Chau Thang rigid bridge construction area (located about 1 km below the old spillway bridge). Photo: Nhat Lan

Currently, Chau Thang bridge is under construction of its foundation. Photo: Nhat Lan

Materials for bridge construction have been delivered. Photo: Nhat Lan

What worries Quy Chau district is that the construction site of Chau Thang bridge is about 5 - 6m lower than National Highway 48, requiring a large amount of land, about 35,000 m3to build the road leading to the bridge, while in the district there are only 4 planned mines but no organization or individual dares to apply for a mining license. Photo: Nhat Lan

The problem of land leveling is also a reality in the project to build an embankment to prevent landslides on the banks of the Hieu River, passing through Tan Lac town (phase 2). In the photo: The project to build an embankment to prevent landslides on the banks of the Hieu River, the area near the foot of Ke Bang Bridge. Photo: Nhat Lan

The completion time of the embankment project to prevent landslides on the Hieu River bank through Tan Lac town is expected at the end of December 2022. To complete, about 28,000 m3land leveling, but is currently in a deadlock. Photo: Nhat Lan

Tan Lac Town Primary School is one of 41 infrastructure projects under 3 National Target Programs. To build the school, Quy Chau district planned the construction site with an area of ​​17,000 m2In the photo: The road to the planned area of ​​Tan Lac Primary School is on the left, a low-lying area about 2m above the road surface. Photo: Nhat Lan

According to the calculation of Quy Chau district, with the low-lying situation of the planning area for the construction of Tan Lac town Primary School, 42,776 m will be needed.3land for leveling. The leveling is expected to be completed in early March 2023. However, due to lack of land for leveling, the leveling cannot be carried out. Photo: Nhat Lan