Construction of a 1km-long road in Quynh Luu that has been unfinished for 10 years continues

Tien Dong DNUM_BAZBBZCACE 20:13

After Nghe An Newspaper reported, the rural traffic route of more than 1km in Quynh Hung commune (Quynh Luu) has continued to be constructed.

According to the information we received, up to this point, the rural traffic route connecting hamlet 11 and hamlet 12 of Quynh Hung commune has been concreted.

Đây là con đường mà học sinh trên địa bàn thường xuyên qua lại. Ảnh: Tiến Đông
The road before being concreted. Photo: Tien Dong
bna_6(1).jpg
The road section has now been concreted and is being paved. Photo: Tien Dong

Previously, on October 11, 2024, Nghe An Electronic Newspaper published an article reflecting"A road of more than 1km long remains unfinished for 10 years in Quynh Luu".Specifically, on June 16, 2014, the People's Committee of Quynh Luu district issued Decision No. 1185/QD-UBND approving the Economic - Technical Report on the project to upgrade and renovate rural roads in Quynh Hung commune. The total length of the project is 1,334.51m (more than 1.3km), divided into 2 routes. Of which, route 1 is 334.51m long, route 2 is 1,000m long. In addition, the routes are also designed with a system of culverts, longitudinal ditches, and slope reinforcement...

Công trình chưa hoàn thành với nhiều hạng mục còn dở dang. Ảnh: Tiến Đông
The route before Nghe An Newspaper reported. Photo: Tien Dong
bê tông
Currently, this road has been paved with clean concrete. Photo: Tien Dong

The total investment of the project is 4,722,501,000 VND, of which the construction cost is 4,079,883,000 VND. The People's Committee of Quynh Hung commune was then assigned to directly manage the project. The implementation period is 12 months from the commencement date.

bna_1(1).jpg
Workers are completing the final stages after pouring concrete. Photo: Tien Dong

Due to the long time of not being able to start construction, on November 14, 2018, the People's Committee of Quynh Luu district had to issue Decision No. 2271/QD-UBND on approving the adjustment of the Technical Economic Report and the Contractor Selection Plan to implement the above project.

bna_10.jpg
A section of the water pipe that was damaged by the residents is being repaired so concrete cannot be poured yet. Photo: Tien Dong

Immediately after that, this project was allocated 2.4 billion VND in capital according to the infrastructure construction investment plan of Quynh Hung Commune People's Committee in 2018. For the remaining amount, Quynh Hung Commune People's Committee committed to mobilizing the commune budget, contributions from people in the beneficiary area and other legal capital sources within 2 years (2019 and 2020).

bna_9.jpg
A section has been leveled waiting for concrete to be poured. Photo: Tien Dong

However, after a short time of starting construction, this project had to stop for a long time due to lack of capital.

It is known that before the concrete pouring time, this project has been completed about 60%, including the foundation and the system of ditches and sewers. The representative of the construction contractor said that currently, taking advantage of the sunny weather, the sections that have been poured with concrete will be completed with curbs and anti-cracking joints. Some sections that have the ground level will strive to be completed this November.