Completion of site clearance for Hai Thuong Lan Ong road project (Vinh city) phase 1

Quang An August 22, 2024 14:26

On the morning of August 22, Comrade Phan Duc Dong - Member of the Provincial Party Standing Committee, Secretary of Vinh City Party Committee directly inspected the construction progress of Hai Thuong Lan Ong Street.

Comrade Phan Duc Dong highly appreciated the active and drastic participation of units in clearing the site of this road, and at the same time requested the City Project Management Board to speed up the progress, strengthen close and regular supervision of the quality of the project; soon complete the construction of drainage ditches and construction on Hai Thuong Lan Ong road to ensure progress.

Đồng chí Phan Đức Đồng - Uỷ viên BTV Tỉnh ủy, Bí thư Thành ủy Vinh kiểm tra tiến độ thi công đường Hải Thượng Lãn Ông. Ảnh: P.V
Comrade Phan Duc Dong - Member of the Provincial Party Committee, Secretary of Vinh City Party Committee inspected the construction progress of Hai Thuong Lan Ong Street. Photo: PV

According to information from the Ha Huy Tap ward authorities, on August 20, Mr. Phan Hong Tien's family, Yen Son block, signed and received compensation for land clearance on Hai Thuong Lan Ong street. This is the last household in the clearance area to have completed the procedures to hand over the land to the project.

bna_1(1).jpg
Mr. Phan Hong Tien's family completed procedures to receive compensation for the recovered land area, and was the last household to complete procedures to hand over the site to the project. Photo: QA

Mr. Ngo Xuan Nam - Vice Chairman of the People's Committee of Ha Huy Tap Ward said: Hai Thuong Lan Ong Street passing through the ward has 15 households whose land must be recovered to expand and upgrade the road. After many months of propaganda and mobilization by the city's functional agencies, the city's Project Management Board and the Ward People's Committee, up to now, 15/15 households have agreed to the compensation plan and handed over the site to the construction unit.

It is known that Hai Thuong Lan Ong route from Truong Van Linh to Bui Huy Bich (phase 1) passes through Ha Huy Tap ward and Nghi Phu commune. In Ha Huy Tap ward, the total area of ​​recovered land is 3,412.8m2.2(including residential land, agricultural land, office land and traffic land). For Nghi Phu commune, the total recovered land area is 1,078.8m2(including residential land and traffic land, (10 households are subject to land acquisition (land handover completed by the end of 2023).

bna_5.jpg
Machinery was mobilized to clear the site after handover on Hai Thuong Lan Ong Street. Photo: QA

According to the reporter's records, Vinh City is currently focusing on mobilizing machinery and human resources to dismantle constructions, while expanding roads and building drainage systems...

Previously, some opinions said that the construction progress of Hai Thuong Lan Ong road project was slow, according to the explanation of Vinh City Project Management Board - the road construction unit said that the reason was because the site clearance had not been completed before, so the construction could not be continuous. However, the site is now available and the city will speed up the construction progress of this road to complete it as soon as possible.

bna_2.jpg
Digging drainage ditches on Hai Thuong Lan Ong street. Photo: QA

According to the plan, Hai Thuong Lan Ong Street will be expanded to 24 meters, from the intersection with Truong Van Linh Street to the planned 24 meter road and implemented in two sections.

Section 1 (from Bui Huy Bich Street to the 24m planned road) according to Decision No. 911/2023 of Vinh City People's Committee, in accordance with the 1/2000 scale zoning plan of Nghi Phu commune and Hung Loc commune, route length 879.41 m, total investment 217.3 billion VND.

As for section 2 (the starting point intersects with Truong Van Linh Street, the ending point intersects with Bui Huy Bich Street), according to Decision No. 2692 of Vinh City People's Committee. This section has a total investment of more than 93.3 billion VND, nearly 200m long. The entire road will be built 24m wide, of which the road surface width is 12m, the sidewalk is 2 x 6m, and the road surface is asphalt.