Conducting compulsory land acquisition at VSIP Nghe An Industrial Park Project
(Baonghean.vn) - On the morning of August 8, the People's Committee of Hung Nguyen district enforced the Decision on land recovery to implement the Project on Construction and Business of Infrastructure of VSIP Nghe An Industrial, Urban and Service Park (Industrial Park, Phase 1B), in Phuc Long hamlet, Hung Tay commune.
The land area being forcibly acquired is 21,105.2 square meters wide.2is agricultural land of 17 households located within the clearance area, in Phuc Long hamlet (Hung Tay commune). This area is within the planning scope of phase 1B,VSIP Nghe An Industrial Park and Urban Areawith a total area of 52.65 hectares, with 330 affected households. 313 households and individuals have received compensation and support for site clearance (reaching a rate of 94.85%), but up to now, 17 households have not received the money. This has affected the overall progress of the project, and at the same time, made many potential investors hesitant when conducting investment research. Although local authorities at all levels have repeatedly mobilized, met, had dialogues, and responded to petitions..., these 17 households still refuse to comply.


Therefore, to ensure the strictness of the law and at the same time not affect the general investment environment of the province, on April 6, 2023, the People's Committee of Hung Nguyen district issued Decision No. 277/QD-UBND on the establishment of a Board to enforce land recovery for households and individuals in Phuc Long hamlet, Hung Tay commune. On July 31, 2023, the People's Committee of Hung Nguyen district also issued Plan No. 37/KH-UBND on Organizing the enforcement of the Decision on land recovery to implement the Project of Construction and Business of Infrastructure of VSIP Nghe An Industrial, Urban and Service Park in Phuc Long hamlet, Hung Tay commune.


On the morning of August 8, the People's Committee of Hung Nguyen district and other functional forces organized enforcement and construction protection in the above-mentioned area. After reading the land recovery decisions, the People's Committee of Hung Nguyen district mobilized machinery and organized leveling of the ground. According to our records, from the beginning, there were still some people who refused to comply and obstructed the construction machinery. However, through propaganda and other professional measures, the construction protection was still carried out smoothly.



The land acquisition and site clearance to hand over to the investor to implement the VSIP Nghe An Industrial Park, Urban and Service Infrastructure Construction and Business Project in Hung Tay Commune, Hung Nguyen District is a correct policy, consistent with the development of the province. In addition to properly implementing the province's investment attraction policy, it also creates conditions for potential investors to come and learn, soon start building factories, investing in production and business according to the set plan.
In particular, at the above land, it is known that a foreign investor has come to survey and is expected to sign an investment commitment as soon as the land is cleared.
According to the latest information, on the morning of August 8, 3/17 households agreed to receive compensation and support for site clearance. The Compensation and Site Clearance Council of Hung Nguyen district will carry out the procedures and pay compensation immediately to the people.