Vinh City organizes construction protection for the project to build a regulating lake.
(Baonghean.vn) - On the morning of July 5, Vinh City People's Committee organized security forces to construct a reservoir project in Hung Loc commune, Vinh City.
The project to build a regulating lake under the Vinh Urban Development Sub-project has a total construction area of 53 hectares, and has been under construction since 2015.
![]() |
The project to build a regulating lake under the Vinh Urban Development Sub-project has a total construction area of 53 hectares. Photo: Vo Huyen |
To implement the project, the People's Committee of Vinh province and city issued decisions approving compensation plans, support for site clearance and agricultural land recovery for affected households in Hung Dung ward, Hung Hoa and Hung Loc communes.
After the plan was made, most households agreed to receive compensation and hand over the site so that the construction unit could start construction. However, there were still 14 households in Hung Loc commune who refused to comply.
Although the People's Committee of Vinh city, Hung Loc commune and related sectors have repeatedly organized dialogues, propaganda, mobilized and explained to households about the necessity of land recovery, these households still have not handed over the land.
![]() |
Vinh City People's Committee organized security forces to protect the construction of a reservoir project in Hung Loc commune. Photo: Vo Huyen |
To ensure the construction progress, Vinh City People's Committee and relevant agencies deployed security forces to protect the construction site and reclaim land to hand over to contractors. The construction security took place safely, however, 6 subjects who resisted and obstructed the construction site were handled by the authorities according to the law./.
Vo Huyen