Yen Thanh speeds up progress of key projects

Article: Van Truong - Editor: Lam Tung DNUM_CGZAEZCACA 07:46

(Baonghean) - Yen Thanh district is focusing on directing site clearance for projects in the area, while actively urging construction units to speed up the progress of key projects.

Speed ​​up construction progress

At this time, the rural traffic route connecting Khanh - Nam - Ly - Minh communes from Co quarry in Nam Thanh commune to hamlet 8 in Minh Thanh commune is being urgently constructed. Mr. Cao Truong Danh - Director of Danh Nhung Company Limited said: Right from the start of construction in early 2020, we have deployed human resources, machinery and equipment to ensure construction progress and quality.

Up to this point, the unit has completed over 30% of the workload. The unit is mobilizing machinery to lower the height and tarpaulin the slope of Truong Gio, the section bordering Nam Thanh and Minh Thanh communes, with a length of nearly 100 m, in accordance with the approved design and techniques. Excess soil and rock are dumped at the disposal area.

According to the Yen Thanh District Project Management Board, this route is more than 4.5 km long, with a total investment of more than 19 billion VND. The road is designed to be 5 meters wide and concreted, with the section from Len Co quarry in Nam Thanh commune to Hamlet 8 in Minh Thanh commune being 1.3 km long. It is expected that this route will be completed by February 2021. Once this route is put into use, it will contribute to promoting the socio-economic development of the communes passing through it.

Đơn vị thi công huy động máy móc để hạ độ cao, bạt mái ta luy dốc Truông Gió đoạn giáp ranh xã Nam Thành và Minh Thành (Yên Thành). Ảnh: V.T
The construction unit mobilized machinery to lower the height and cover the slope of Truong Gio slope at the border of Nam Thanh and Minh Thanh communes (Yen Thanh). Photo: Van Truong

Yen Thanh is also speeding up the construction progress of Bach Lieu Secondary School. Since the beginning of 2020, a 3-storey classroom building has been completed. Currently, construction of items such as the school's headquarters and restrooms, gates, yards, fences and auxiliary items, and the construction of dormitories and dining halls are continuing.

To speed up the progress and improve the quality of the project, all load-bearing frames and floors are poured with fresh concrete. The District People's Committee assigned the Project Management Board to supervise, inspect and supervise the quality of the project, and bring in construction materials to ensure quality. According to the plan, this project will be put into use by the end of 2020. Currently, the school has increased from 12 classes to 16 classes, and the school's constructions put into use will help the school not have to study overtime like before.

Trường THCS Bạch Liêu, thị trấn Yên Thành thi công xong các phòng học khang trang. Ảnh: Văn Trường
Bach Lieu Secondary School, Yen Thanh town, has completed construction of spacious classrooms. Photo: Van Truong

To serve flood drainage for the upcoming rainy season, the Yen Thanh District Construction Project Management Board is actively urging the progress of the project "Project to upgrade and reinforce the flood drainage system and flood protection dykes of Yen Thanh District, Phase I". This project belongs to the target program to respond to climate change, mainly focusing on dredging canals and constructing a number of bridges over 4.5 km long.

Currently, the construction unit is implementing phase 1, basically completing over 75% of the volume. This year's rainy season will drain floods for Hoa Thanh, Van Thanh, Nhan Thanh, Tang Thanh, Vinh Thanh communes... The rescue route, the road inside Yen Thanh town to Duc Thanh is also being accelerated.

To ensure the progress of construction projects in the district, since the beginning of the year, we have directed and urged contractors to concentrate human resources, equipment, and machinery. Together, we have resolved difficulties and accompanied businesses during the construction process. At the same time, we also require construction units to strictly implement isolation measures such as wearing masks, workers must keep a distance of more than 2 meters when working, and avoid gathering before and after working hours.
Currently, some completed projects put into use have promoted efficiency, improved capacity to serve production, prevent floods and storms, and mitigate natural disasters such as the craft village road in Long Thanh commune, the project to upgrade the flood drainage system of Bau Chen - Trung Long river from Cong Thanh commune to Long Thanh...

Mr. Pham Quang Sang - Deputy Director of Yen Thanh District Construction Project Management Board


Focus on removing difficulties in land acquisition and clearance

Besides the advantages, Yen Thanh district still faces many difficulties in site clearance work in some projects. Specifically, the projects: Rescue and relief road of Song So commune, Phu Thanh commune, along Vach Bac canal, is currently stuck with agricultural land of over 200 households. The main road in the first phase of Yen Thanh town is also stuck with site clearance for over 20 households...
Mr. Nguyen Thanh Ha - Vice Chairman of Yen Thanh District People's Committee said: According to the plan, from now until the end of 2020, Yen Thanh district will focus on directing the resolution of difficulties to speed up the construction progress and disbursement of projects that have been allocated capital. In conjunction with the development of public investment plans, Yen Thanh district will balance capital sources in order of priority. Accordingly, debt repayment for projects that have been settled, completed projects that have been put into use but have not been settled, transitional projects to ensure the effective promotion of investment capital, weak projects, if there is any capital left, it will be allocated to new investment projects.

chú thích
In recent times, investment in basic construction in Yen Thanh district has been implemented quite well and synchronously. Photo: Van Truong
In recent times, the investment in basic construction in Yen Thanh district has been implemented quite well and synchronously, thanks to the good planning, survey and design, appraisal of projects and strengthening of construction management, especially the progress of key projects. At the same time, the district has done a good job of site clearance and regularly paid attention to and promptly resolved difficulties and obstacles for construction units, so the projects and investment works have been implemented with guaranteed progress and quality.

Speeding up the construction progress of basic construction works in Yen Thanh area to ensure the completion and handover of works for use according to plan such as traffic routes, water systems, promoting efficiency in serving local economic development...

Huyện Yên Thành (Nghệ An) về đích Nông thôn mới

Yen Thanh District (Nghe An) reaches the New Rural Finish Line

(Baonghean.vn) - The voting results showed that 100% of the votes of the members of the Provincial New Rural Area Appraisal Council agreed that Yen Thanh had met the standards of a new rural district. In addition, 14 communes of 5 districts were also voted to meet the standards of a new rural area in this round.