The North-South Expressway, Nghi Son - Dien Chau section, is determined to open to traffic on the occasion of National Day, September 2.

PV Group July 22, 2023 16:39

(Baonghean.vn) - Currently, contractors are focusing on human resources and equipment to speed up construction progress so that the Nghi Son - Dien Chau route can be opened to traffic on the upcoming National Day holiday, September 2.

bna_quỳnh lưu 2.jpg
The North-South Expressway project, Nghi Son - Dien Chau section, is 50 km long, starting at Nghi Son (Thanh Hoa - at the end of the Mai Son - National Highway 45 intersection) and ending at Dien Thap commune (Dien Chau, Nghe An - at the intersection with Dien Chau - Bai Vot Expressway). In Nghe An, this expressway section is 43.5 km long, passing through the following localities: Hoang Mai Town, Quynh Luu, Yen Thanh, Dien Chau. In the photo: Construction of the North-South Expressway section through Quynh Tan commune, Quynh Luu district. Photo: PV
bna_quỳnh lưu 3.jpg
The route was started on July 2, 2021 and is scheduled to be completed in July 2023. However, the possibility of completing the project on the above schedule is unlikely. A representative of Project Management Board 6 - Ministry of Transport said: After removing obstacles in terms of site clearance, in the past time, the unit and contractors have been rushing to construct and set a goal of "finishing" on September 2. In the photo: Construction vehicles day and night on the Nghi Son - Dien Chau route. Photo: PV
bna_Quỳnh Lưu.jpg
The North-South Expressway section passing through Quynh Luu district is gradually taking shape. Photo: PV
bna_hoàng mai 1.jpg
With a length of 50 km, the road section width of phase 1 is 4 lanes (2 lanes on each side), the North - South expressway project, Nghi Son - Dien Chau section, has a total investment of more than 7,200 billion VND, the traffic speed is 80 km/h (the maximum speed of phase 2 after completion is 120 km/h). After the next project, National Highway 45 - Nghi Son, is scheduled to open to traffic this year, from Hanoi to Dien Chau (Nghe An), if traveling by expressway, the journey and travel time will be shortened by half compared to the present. In the photo: Construction machinery of the North - South expressway through Hoang Mai town. Photo: PV
bna_trường vnh.jpg
Truong Vinh Tunnel connecting Thanh Hoa and Nghe An on the North-South Expressway (constructed by Deo Ca Group) has been open to traffic since 2022. Currently, contractors are completing the final traffic safety items inside the tunnel. Photo: PV
bna_đúc dải phân cách.jpg
Workers are making road dividers on the highway. Photo: PV
bna_diễn yên.jpg
For contractors who are behind schedule, do not complete the construction volume at the site, and are unable to make up for the delayed progress, Project Management Board 6 will base on the provisions of the contract and relevant legal provisions to consider transferring the volume and handle violating contractors according to regulations. In the photo: North-South Expressway section through Dien Yen commune, Dien Chau district. Photo: PV
bna_Đô Thành.jpg
Construction machinery works at night to keep up with progress in Do Thanh commune, Yen Thanh district. Photo: PV
bna- nut giao Quỳnh Vinh .jpeg
A representative of Project Management Board 6, Ministry of Transport, said: As of early July, the project had just resolved the final issues regarding the site, from which the contractors focused on synchronous construction along the entire route. The unit is directing the contractor to concentrate machinery, equipment, and human resources to take advantage of favorable weather before the rainy season to deploy vigorously, work overtime, and increase shifts to ensure completion according to the set schedule. Photo: Quynh Vinh Intersection, Hoang Mai Town. Photo: PV