Focus on solving problems in site clearance of VSIP Nghe An Industrial Park 1
On the morning of December 17, Comrade Nguyen Duc Trung - Secretary of the Provincial Party Committee, Chairman of the Provincial People's Committee chaired a meeting to resolve problems in site clearance for the VSIP Nghe An 1 Urban and Service Industrial Park project and propose investment in the VSIP Nghe An 3 Industrial Park project.
Attending the meeting were comrade Bui Thanh An - Member of the Provincial Party Standing Committee, Vice Chairman of the Provincial People's Committee; leaders of departments, branches, Vinh city, Hung Nguyen district and VSIP Nghe An Company Limited.

Problems with site clearance of nearly 7.4 hectares
Opening the meeting, Provincial Party Secretary and Chairman of the Provincial People's Committee Nguyen Duc Trung affirmed that the province's FDI attraction results in 2024 up to this point are very encouraging, expected to reach nearly 1.7 billion USD, mainly concentrated in industrial parks.
Praising and appreciating VSIP Nghe An Company Limited for its efforts to attract more than 1 billion USD in investment in 2024, thereby contributing greatly to the province's FDI attraction results, the Provincial Party Secretary and Chairman of the Provincial People's Committee said that in order for the province to continue to have conditions to attract investment, it is necessary to resolve difficulties in industrial parks, including VSIP Nghe An 1 Industrial Park.

VSIP Nghe An Urban and Service Industrial Park was officially established in 2015 with an area of up to 750 hectares. The project was invested and constructed by VSIP Nghe An Company Limited, a member of VSIP Group.
To date, this industrial park has attracted 55 secondary investor projects with a total capital of over 2,063 billion USD, including 34 FDI projects with a total investment of over 1,976 billion USD; the occupancy rate is about 97%.

The site clearance work has been completed on 681.1 hectares to date; 61.51 hectares remain in their current state without site clearance. There are still 7.39 hectares that have not been cleared, including 3.74 hectares of agricultural land; 3.65 hectares of cemetery land.
According to the Southeast Economic Zone Management Board, in Hung Nguyen district, there are 3.65 hectares of existing cemetery land without a relocation plan, and the district has not completed the inventory and approved the compensation plan for site clearance. In addition, there are 3.3 hectares of agricultural land that have not been cleared because 2 households have not agreed to receive money and requested additional compensation.

In Vinh city, there is still 0.18 ha of agricultural land that is completing documents to submit for appraisal of the plan; 0.15 ha of land has not been cleared due to tombs, electric poles and 220kV, 110kV and 35kV power lines.
To continue attracting investment, VSIP Nghe An Company Limited has sent an official dispatch requesting approval of the location for the VSIP Nghe An 3 Industrial Park Project in Industrial Park No. 8 with a scale of 220 hectares in Hung Tay commune, Hung Nguyen district.

The Provincial People's Committee has assigned the Hung Nguyen District People's Committee to organize the establishment of a 1/2000 scale construction zoning plan for Industrial Park No. 8 in Hung Tay Commune. Hung Nguyen District is selecting a consulting unit to establish a 1/2000 scale construction zoning plan for Industrial Park No. 8.
At the meeting, leaders of localities, departments, branches and Nghe An Electricity Company reported on the progress of resolving issues related to site clearance.
Speed up site clearance
Concluding the meeting, Secretary of the Provincial Party Committee and Chairman of the Provincial People's Committee Nguyen Duc Trung emphasized that in the past time, the sectors and localities have made efforts to remove obstacles and difficulties, especially the site clearance of VSIP 1 Industrial Park; however, there are still many difficulties in the 7.39ha area, so it is recommended to focus on implementation, in which trying to complete before January 15, 2025.

To complete the above timeline, the Provincial Party Secretary and Chairman of the Provincial People's Committee requested Hung Nguyen district to urgently complete the inventory, count, and approve the compensation and resettlement support plan for graves within the existing 1.7ha cemetery area.
At the same time, conduct a survey and select a location to relocate graves within an area of 1.95 hectares of existing cemetery land in the Urban and Service Area Phase 3 before May 31, 2025.
Assign Vinh city to carry out investment procedures to build and complete a new cemetery in Hung Chinh commune to serve the relocation of 1.7 hectares of existing cemetery land, to be completed before May 31, 2025, in which it is noted that only existing graves will be relocated.

Regarding 3.3 hectares of agricultural land in Hung Nguyen district, the Provincial Party Secretary and Chairman of the Provincial People's Committee requested the authorities to strengthen mobilization and convince people to understand and agree, and try to complete the clearance before February 28, 2025.
At the same time, Vinh city completed the compensation file for site clearance of 0.18ha of agricultural land, to be completed before February 28, 2025. Vinh city completed the relocation of 0.15ha of graves before May 31, 2025.

Vinh City completes the paperwork to relocate the 220kV, 110kV and 35kV lines before December 31, 2024 for construction and relocation of these lines before April 30, 2025. Relevant departments, branches, Nghe An Power Company, Nghe An Power Transmission consider and handle the contents according to their authority.
The Provincial Party Secretary and Chairman of the Provincial People's Committee also requested that from now until before the Lunar New Year 2025, Vinh City will handle environmental sanitation, infrastructure management, urban embellishment on the 72m road, and strictly handle the illegal dumping of waste on this road. Departments and branches should consider and have a plan to include in the 2026 - 2030 Medium-term Public Investment Plan to complete the entire road.

The head of the Provincial Party Committee and the Provincial People's Committee also requested the People's Committee of Hung Nguyen district to continue to quickly carry out the task of establishing a 1/2000 scale construction zoning plan for Industrial Park No. 8 in Hung Tay commune. The sectors will guide Hung Nguyen district to implement in accordance with regulations and ensure progress.
The Southeast Economic Zone Management Board presides over and coordinates with agencies to advise the Provincial People's Committee on the conditions for establishing Industrial Park No. 8 before March 31, 2025.
The Provincial Party Secretary and Chairman of the Provincial People's Committee also requested VSIP Nghe An Company Limited to focus resources on speeding up the implementation of the urban and service area project; and to allocate funds to build a cemetery in the Urban and Service Area Phase 5A.

Agreed to carry out procedures for investment policy of Hung Tay - Do Luong power line. Nghe An Electricity Company is interested in ensuring electricity supply for VSIP 1 Industrial Park and secondary investors in the industrial park.
The Management Board of the Southeast Economic Zone regularly monitors and urges sectors and localities to perform their tasks, promptly reports arising issues to the leaders of the Provincial People's Committee for resolution.