Week 2, April 2025: Nghe An starts construction of 1,097 houses for the poor

Plum Blossom DNUM_BBZAEZCACF 19:29

From April 4 to 10, the program to mobilize and support the poor and households with difficult housing circumstances continued to be promoted by both the political system and the social community, with a total of 1,097 new houses started and 492 completed and handed over for use.

 Huyện Quỳnh Lưu huy động cán bộ trong hệ thống chính trị làm nhà ở cho dân. Ảnh
Quynh Luu district mobilized officials in the political system to build houses for people. Photo: Mai Hoa

According to the update of the Provincial Fatherland Front Committee in 20 districts, cities and towns; in week 2, April 2025 (from April 4 to 10), the whole province continued to start construction of 1,097 houses (445 new houses, 652 houses repaired).

Of the total 1,097 houses, 516 houses (247 newly built, 269 repaired) are funded by social funds under the province's Program 1838; 235 houses (44 newly built, 191 repaired) are funded by the 2 National Target Programs; 346 houses (154 newly built, 192 repaired) are funded by the Housing Support Program for People with Merits.

ketquakhoicongtuan2.png
Results of house construction groundbreaking in week 2, April 2025 in the whole province. Graphics: Huu Quan

Details of the number of new houses started during the week in 16 localities (data from high to low): Tuong Duong district started construction of 514 houses (148 new houses, 366 repaired houses); Thanh Chuong district started construction of 138 houses (61 new houses, 77 repaired houses); Nghia Dan district started construction of 62 houses (41 new houses, 21 repaired houses); Nam Dan district started construction of 52 houses (41 new houses, 11 repaired houses); Con Cuong district started construction of 40 houses (30 new houses, 10 repaired houses).

 Cán bộ Mặt trận các cấp huyện Đô Lương hỗ trợ làm nhà cho hộ nghèo tại xã Nam Sơn.
Officials of the Fatherland Front at all levels in Do Luong district support poor households in Nam Son commune to build houses. Photo: Mai Hoa

Ky Son district started construction of 39 houses (28 new houses, 11 repaired houses); Yen Thanh district started construction of 34 houses (18 new houses, 16 repaired houses); Do Luong district started construction of 31 houses (13 new houses, 18 repaired houses); Quy Chau district started construction of 26 houses (18 new houses, 8 repaired houses); Nghi Loc district started construction of 24 houses (5 new houses, 19 repaired houses).

Hung Nguyen district started construction of 15 houses (4 new houses, 11 repaired houses); Vinh city started construction of 15 houses (3 new houses, 12 repaired houses); Anh Son district started construction of 14 houses (4 new houses, 10 repaired houses); Thai Hoa town started construction of 7 houses (5 new houses, 2 repaired houses); Dien Chau district started construction of 4 houses (3 new houses, 1 repaired house); Quynh Luu district started construction of 1 new house.

chitietnhakhoicongmoi.png
Details of the number of new housing constructions started this week in 16 localities (data from high to low). Graphics: Huu Quan

The result of completion, handover and putting into use of housing in week 2, April 2025 in the whole province is 492 houses (261 newly built houses, 231 repaired houses).

Of which, the source from Program 1838 is 174 houses (146 newly built houses, 28 repaired houses); the source from 2 National Target Programs is 133 houses (64 newly built houses, 69 repaired houses); the source from the Housing Support Program for Meritorious People is 185 houses (51 newly built houses, 134 repaired houses).

ketquahoanthanhtuan2.png
Results of completion, handover, and putting into use of housing for the poor in week 2, April 2025 in the whole province. Graphics: Huu Quan

Details of the number of houses completed, handed over, and put into use in week 2, April 2025 in 15 localities (data from high to low): Ky Son district completed 107 houses (87 new houses, 20 repaired houses); Tuong Duong district completed 74 houses (24 new houses, 50 repaired houses); Yen Thanh district completed 72 houses (40 new houses, 47 repaired houses); Con Cuong district completed 56 houses (51 new houses, 5 repaired houses).

Hung Nguyen district completed 24 houses (8 new houses, 16 repaired houses); Nghi Loc district completed 23 houses (17 new houses, 7 repaired houses); Anh Son district completed 23 repaired houses; Do Luong district completed 18 houses (3 new houses, 15 repaired houses); Vinh city completed 16 houses (2 new houses, 14 repaired houses).

Nam Dan district completed 14 houses (5 new houses, 9 repaired houses); Quynh Luu district completed 11 houses (10 new houses, 1 repaired house); Dien Chau district completed 8 houses (6 new houses, 2 repaired houses); Nghia Dan district completed 4 houses (3 new houses, 1 repaired house); Quy Chau district completed 4 repaired houses; Hoang Mai town completed 1 new house.

chitietnhahoanthanh.png
Details of the number of houses completed, handed over, and put into use in week 2, April 2025 in 15 localities (data from high to low). Graphics: Huu Quan

In the second week of April 2025, district-level units received VND 1,394 million from support sources; disbursed VND 4,564 million from socialized sources.

 Lãnh đạo huyện Quỳnh Lưu kiểm tra, đốc thúc tiến độ làm nhà ở cho người có hoàn cảnh khó khăn về nhà ở.
Quynh Luu district leaders inspect and urge the progress of housing construction for people with housing difficulties. Photo: Mai Hoa

In total, when implementing the program to mobilize and support the construction of houses for the poor and households with difficult housing circumstances, from February 2, 2023 to April 10, 2025; the whole province has built and repaired 14,827 houses (11,047 new houses, 3,780 houses repaired).

Of which, the Socialized Support Program: 8,818 houses (7,498 new houses, 1,320 repaired houses); 2 National Target Programs: 5,224 houses (3,281 new houses, 1,943 repaired houses); Housing support program for meritorious people: 785 houses (268 new houses, 517 repaired houses).

 Người dân huyện Thanh Chương hỗ trợ làm nhà ở cho hộ có hoàn cảnh khó khăn.
Thanh Chuong district residents support housing construction for households in difficult circumstances. Photo: Mai Hoa

Thus, the total number of remaining houses to be completed before July 31, 2025 is 6,422 (3,960 new houses, 2,792 repaired houses). Of which, the Socialized Source Program is 1,928 houses (1,149 new houses, 779 repaired houses); 2 National Target Programs are 1,617 houses (857 new houses, 760 repaired houses); The Housing Support Program for People with Meritorious Services to the Revolution is 2,877 houses (1,624 new houses, 1,253 repaired houses).