In June 2019, the adjustment of land use planning of Vinh International Airport will be announced.

Dinh Nguyet DNUM_DAZAFZCABJ 19:10

(Baonghean.vn) - That was one of the contents brought up at the working session between the Provincial People's Committee and the Steering Committee for implementing projects at Vinh International Airport invested by Vietnam Airports Corporation, on the afternoon of May 30.

Comrade Le Hong Vinh - Member of the Provincial Party Committee, Vice Chairman of the Provincial People's Committee chaired the meeting; representatives of leaders of relevant departments and branches and members of the Steering Committee for implementing projects at Vinh International Airport attended the meeting.

Problems in project implementation

At the meeting, representatives of Vietnam Airports Corporation reported on the current implementation of projects at Vinh International Airport such as: Project to install passenger bridges; Project to expand and renovate aircraft parking; project to build passenger terminal T2; project to build the airport parking lot in front of terminal T2; works within the scope of the project that need to be relocated to implement the project to build terminal T2 and the parking lot in front of terminal T2.

Representative of Vietnam Airports Corporation reports on the implementation of projects at Vinh International Airport. Photo: Sy Hung
The unit also reflected the difficulties and obstacles that the Provincial People's Committee requested to be directed to resolve, such as: The work of setting up planning markers; The land acquisition stakes have not been handed over yet, so the Vinh City People's Committee has no basis to implement the steps to implement the land acquisition; difficulties in the process of implementing the task of making detailed plans for the construction of the civil aviation functional area - Vinh International Airport; regarding the area of ​​6.3 hectares of land north of the runway, the Provincial People's Committee has sent documents to relevant ministries and branches but there is no solution; difficulties in the work of registering land use needs to implement the project.

Phối cảnh dự án nâng cấp, mở rộng Cảng hàng không Quốc tế Vinh. Ảnh tư liệu
Perspective of the project to upgrade and expand Vinh International Airport. Photo: Archive

After listening to the report, representatives of relevant departments and units focused on discussing and proposing solutions to remove difficulties, speed up the planning progress of the T2 terminal project, the basis for units to proactively implement site clearance; request Vinh City to soon announce the adjustment of the land use planning of Vinh International Airport; the issue of reviewing site clearance and marking planning markers...

Vice Chairman of Vinh City People's Committee Le Sy Chien said that the City will organize the announcement of the land use planning of Vinh International Airport on June 5, 2019. Photo: Sy Hung

Vice Chairman of Vinh City People's Committee Le Sy Chien said that the City will organize the announcement of the land use planning of Vinh International Airport on June 5, 2019, and at the same time print documents to send to relevant departments and branches; print billboards and posters to inform all people...

Early completion of approval of detailed construction planning 1/500

Concluding the meeting, Vice Chairman of the Provincial People's Committee Le Hong Vinh emphasized: Infrastructure at Vinh International Airport has been invested in over the past years, serving the needs of the people and socio-economic development.

Vice Chairman of the Provincial People's Committee Le Hong Vinh requested that relevant departments, branches and units coordinate to remove difficulties to ensure project progress. Photo: Sy Hung

"Projects at Vinh International Airport are being implemented, helping to diversify Nghe An's transportation activities, creating convenience for people, and contributing to the province's economic and social development."

Vice Chairman of Provincial People's Committee Le Hong Vinh

To ensure the progress of the projects, the Vice Chairman of the Provincial People's Committee requested ACV to work with the Civil Aviation Authority of Vietnam to soon complete the approval of the detailed construction plan of 1/500 for the aircraft parking project in front of Terminal T2; complete the procedures for submitting the project to competent authorities for appraisal and approval in 2019; work with the State Capital Management Committee and relevant ministries to agree on the funding source for land acquisition and clearance of the 6.3ha area at the beginning of the runway.

After Vinh City People's Committee coordinates to announce the planning in early June, ACV is requested to coordinate to soon set up land acquisition markers, develop a relocation plan, and arrange funds to carry out payment and compensation work.

Overview of the working session. Photo: Sy Hung

The Vice Chairman of the Provincial People's Committee assigned Vinh City to soon organize the announcement of the land use plan for Vinh International Airport; preside over and coordinate with relevant departments, branches and units to review and determine the land area that needs to be cleared for project construction, the location of resettlement works to submit to the Provincial People's Committee to adjust the land use plan. At the same time, strengthen propaganda and mobilization, so that people in the area affected by the project, so that people understand and accompany the province; strengthen security and order inside and outside the airport area, and management of construction planning in Vinh airport.

The Department of Transport shall coordinate with the Vinh City People's Committee to monitor and grasp difficulties and obstacles in the process of site clearance and project construction to report to competent authorities for consideration and resolution. The Department of Natural Resources and Environment, the Department of Finance, and the Department of Construction shall continue to coordinate and perform well the assigned tasks./.